IntelliGrid Architecture

 

 

Home

Parent Menu

Overview of Functions
Market Operations
Transmission Operations
Distribution Operations
HV Generation
Distributed Resources
Customer Services
List of IT Use Cases
List of Functions

Same Level Menu

Data Acquis & Control
ADA Overview
DOMA
Fault Loc, Iso, & Restore
Volt Var Optim
Contingency Analysis
Multi Feeder Reconnect
Intelligent Alarms
Coordinate Emergency
Coordinate Restoration
Pre-arm Remedial
Relay Re-coordination
List of Distrib Use Cases

Child Menu

 

Search IntelliGrid Site

Questions/Comments

Questions

 

Responses

 

 

Distribution Operations - Multi-Level Feeder Reconfiguration Function

Contents

Narrative

This application recommends an optimal selection of feeder(s) connectivity for different objectives. It supports three modes of operation:

1.    Closed-loop mode, in which the application is initiated by the Fault Location, Isolation and Service Restoration application, unable to restore service by simple (one-level) load transfer, to determine a switching order for the remotely-controlled switching devices to restore service to the non-faulted sections by using multi-level load transfers. .

2.    Advisory mode, in which the application is initiated by SCADA alarms triggered by overloads of substation transformer, segments of distribution circuits, or by DOMA detecting an overload, or by operator who would indicate the objective and the reconfiguration area. In this mode, the application recommends a switching order to the operator.      

3.    Study mode, in which the application is initiated and the conditions are defined by the user.

The application performs a multi-level feeder reconfiguration to meet one of the following objectives:

a.       Optimally restore service to customers utilizing multiple alternative sources. The application meets this objective by operating as part of Fault Location, Isolation and Service Restoration.

b.      Optimally unload an overloaded segment. This objective is pursued if the application is triggered by the overload alarm from SCADA, or from the Distribution Operation Modeling and Analysis, or from Contingency analysis. These alarms are generated by overloads of substation transformer or segments of distribution circuits, or by operator demand.

c.       Minimize losses

d.      Minimize exposure to faults

e.       Equalize voltages

The last three objectives are selected by engineer/planner.

The feeder reconfiguration process is a multi-objective function with a very large number of variables.  Theoretically, the number of possible combinations to consider during the search of the best solution is equal 2n, where n is the number of switching devices in the interconnected circuits.  With DERs connected to the distribution circuits, the circuit configuration solution may be different.  Just by adding the two states of DER: ON or OFF, the number of combinations for searching the configuration solution increases to 2n+m, where m is the number of DERs connected to the subject circuit.  Different modes of operation and different load schedules of DER can also change the solution.  Hence, the number of combination may increase even more.  The nominal optimal configuration is typically selected for a long-term interval (season, year).  If the solutions are different with DERs ON from those with DERs OFF, then the application should take into account the probable schedules of the DERs during the entire time interval for which the configuration solution is sought and find a configuration which is the best for this time interval.  The application should be capable of recommending smaller time intervals with different circuit boundaries.  

When the reconfiguration solution implies the participation of DER devices, and the circuits can be overloaded if the DER devices are disconnected, then an additional condition that the DER devices are always available when needed by the Area EPS should be present. In this case the maintenance of DER devices will lead to temporary change of configuration, and an outage of DER at heavy-load times is a contingency.   Hence, DERs introduce additional opportunities and additional constraints to the configuration and to the migration from one configuration to another.  

When the distribution circuits are reconfigured, a DER may move from being electrically connected to one substation bus to being connected to another bus, and this may be unacceptable by the DER owner due to, e.g., a change of the DER capability to provide ancillary services, or due to an increase in exposure to faults.  (The DER owner may have a reliability guarantee or similar agreement with DISCO, limiting the exposure to faults.)  The input data describing such kind of conditions should be made available to the reconfiguration application.

Other constraints can be imposed by the transient process during switching operations while implementing the new configuration, which consist of paralleling and breaking.  The change in voltage magnitude and phase angle during the switching operations will present some kind of disturbance for the DER and in some instances may be unacceptable.  Such parameters as acceptable rate of voltage and angle changes may be needed for deciding whether the configuration with a DER connected to the circuit can be accomplished.  In some cases, a temporary intentional islanding during the transition from one configuration to another can be included in the reconfiguration solution. 

The specific of multi-level feeder reconfiguration process is that the more connectivity alternatives are available, the greater are the optimization benefits. As was mentioned above, the number of alternatives increases with the increase of the number of sectionalizing and transfer switching devices.  In order to consider the maximum number of alternatives all interconnected feeders with all switching devices available for control should be included in the optimization process. The presence of DER devices in the distribution system increases the number off alternatives due to the various combinations of kW and kvar injections, possibilities of islanding, and protection schemes, and contractual agreements. The run-times of the multi-level feeder reconfiguration program ranges from seconds to hours depending on the reconfiguration objective.  

The feeder reconfiguration solution will be used for different timeframes, such as:

1.      For several hours after clearing a fault for service restoration to healthy sections. The solution should be found in the matter of seconds.

2.      For several hours or days for voltage equalization, when there is an urgent need in load reduction via Volt, Var, and Watt control. The solution should be found in the matter of minutes.

3.      For several days or weeks for load balancing during maintenance of distribution facilities. The solution should be found in the matter of seconds. The solution should be found in the matter of tens of minutes.

4.      For a season or a year for minimization of customer exposure to interruptions, normal load balancing, and loss minimization. The solution should be sought during several hours.

The input data for this computing application shall include the following DER object model attributes for different reconfiguration objectives and different timeframes:

a.       For minimizing exposure of the distribution system to customer interruptions, the following attributes of the DER object model (or other sources of information) will be used:

·        Rated characteristics

·        Long-term operation and maintenance schedules

·        Contractual constraints

·        Conditions for automatic islanding

b.      For balancing loads of substation transformers and distribution feeders, the following attributes may be needed:

·        Rated characteristics, including the capability curves

·        Short-term operation and maintenance schedules

·        Contractual constraints

c.       For equalizing voltages between feeders and substations, the following attributes should be considered:

·        Rated characteristics, including the capability curves

·        Short-term operation and maintenance schedules

·        Contractual constraints

·        P-Q-V modes of operations

·        Availability to start DER devices in Area EPS demand

d.      For minimizing energy losses, in addition to the attributes mentioned above, the cost of DER operations will be needed.

 

 

IntelliGrid Architecture
Copyright EPRI 2004