Distribution Operations - Brief Use Cases
D-1 Long term distribution planning (1 year to 5 years)
D-1.1 Distribution planners forecast loads for the long term by area
D-1.2 Distribution planners plan distribution upgrades and additions in
accordance with the long-term transmission plan (using planning simulation and
optimization software)
D-1.2.1 New T/D substations
D-1.2.2 New distribution circuits/conductors
D-1.2.3 New distribution transformers
D-1.2.4 New distributed generation, including distributed resources impact
studies
D-1.2.4.1 DisCo plans utility-owned DR to meet reliability and power quality
targets
D-1.2.4.2 DisCo acquires DR base information (to provide ratings and device
models)
D-1.2.4.3 DisCo analyzes DR interconnection to the power system
D-1.2.5 New circuit boundaries
D-1.2.6 New switch allocation
D-1.2.7 New capacitor allocation
D-1.3 Distribution planners plan distribution automation
D-1.3.1 SCADA
D-1.3.2 DA functions
D-1.3.2.1 Fault Location
D-1.3.2.2 Fault isolation and service restoration
D-1.3.2.3 Outage statistics calculations
D-1.3.2.4 Volt/Var control
D-1.3.2.5 Planned outage management
D-1.3.2.6 Feeder reconfiguration
D-1.3.2.7 Cold load pickup
D-1.3.2.8 Dynamic limit calculations
D-1.3.2.9 Feeder paralleling
D-1.3.2.10 Integration with EMS/MOS
D-1.3.2.11 Equipment monitoring and diagnostics
D-1.3.2.12 Other
D-1.4 Distribution planners prepare long-term contracts with transmission
companies covering mutual obligations for the T&D interfaces, operation
coordination, and information exchange
D-1.5 Distribution planners prepare long-term contracts with generators
connected to distribution
D-1.6 Distribution planners prepare long-term contract with customers regarding
service reliability and power quality
D-1.7 Distribution planners generate requirements for information support of
distribution domain activities
D-1.8 Distribution planners update the future layers of relevant databases
D-2 Short-term distribution planning (1 week to 1 year)
D-2.1 Short-term load forecast
D-2.1.1 Load forecast for existing nodal loads
D-2.1.2 Forecast of allocation and amount of new loads
D-2.1.3 Forecast/scheduling of distributed resources
D-2.2 Update of circuit boundaries
D-2.3 Update of switch placement
D-2.4 Update of capacitor placement and sizing
D-2.5 Update of no-load tap positions
D-2.6 Update phase load allocation for better load and voltage balancing
D-2.7 Update of contracts with transmission company
D-2.8 Update of automation settings
D-2.9 Short-term distributed resources impact studies
D-2.10 Update of contracts with distribution generators
D-2.11 Update of contracts with customers
D-2.12 Contractor /Builder requests new service connection (see IEC WG14 Use
Case #2 and 3)
D-2.13 Update of relevant databases
D-2.14 Prepare maintenance plan
D-2.14.1 Calculate system utilization based on forecast load and nameplate
ratings
D-2.14.2 Schedule maintenance operations - time-based
D-2.14.3 Schedule maintenance operations - predictive, based on data and models
D-2.14.4 Schedule equipment replacement - based on age of equipment
D-2.14.5 Schedule equipment replacement - predictive, based on data and models
D-2.14.6 Schedule equipment replacement - based on contingency scenarios
D-2.14.7 Schedule spare distribution, ensure sufficient at each site
D-3 Operational planning (1 day to 1 week ahead)
D-3.1 Planned outage management by using DA applications in study/look-ahead
mode and DA databases
D-3.1.1 Outage request analysis and scheduling, taking into account the
capabilities of real-time DA functions
D-3.1.2 Planners/operators perform load analysis of substation equipment based
on data
D-3.1.3 Multi-level feeder reconfiguration
D-3.1.4 Contingency analysis/reliability (risk) assessment
D-3.1.5 Distributed resources re-scheduling
D-3.1.6 Protection coordination analysis
D-3.1.7 Switching order generation for facilitating the planned outages and for
return to normal
D-3.2 Work management (planning stage)
D-3.2.1 Schedulers interface with contractors
D-3.2.2 Schedulers schedule work crews for scheduled work
D-3.2.3 System operators review and approve scheduled work
D-3.2.4 Schedulers identify assets required for scheduled work
D-3.2.5 Work crews perform scheduled work, coordinating with operators for
switching operations
D-3.3 Operators prepare (plan) for storm conditions and other alerting
situations based on weather data, other alarming systems, and history
D-3.3.1 Change recloser settings
D-3.3.2 Change alarm thresholds
D-3.3.3 Prepare for transformer clipping (e.g. Solar wind raising ground DC
offset)
D-4 Real-time operations
D-4.1 SCADA system monitors distribution system
D-4.1.1 Monitor plant state (open/close)
D-4.1.2 Monitor system activity and load (current, voltage, frequency, energy)
D-4.1.3 Monitor equipment condition (overheat, overload, battery level,
capacity)
D-4.1.4 Monitor environmental (fire, smoke, temperature, sump level)
D-4.1.5 Monitor security (door alarm, intrusion, cyber attack, audio/video
recording)
D-4.2 Operators handle alarms
D-4.2.1 Intelligent alarm processing by SCADA system
D-4.2.2 Distribution of alarms to non-operators
D-4.3 Operators dispatch field crews for scheduled work
D-4.3.1 Crew acquires drawings, previous records, customer profile
D-4.3.2 Operator establishes limits on what crew is permitted to do
D-4.3.3 Using mobile radio system
D-4.3.4 Using mobile computing
D-4.4 Work crews provide information for updating relevant databases
D-4.4.1 Work crews log activities and results of tests
D-4.4.2 Work crews identifies assets installed and/or removed
D-4.5 Operators perform supervisory and/or manual (using field crews) control of
switching operations, load tap changers and voltage controllers, capacitor
statuses
D-4.6 Operator defines objectives and other parameters of DA functions, e.g
D-4.6.1 Closed-loop control of service restoration function
D-4.6.2 Use emergency limits for service restoration
D-4.6.3 Provide volt/var support for transmission
D-4.6.4 Provide Peak Load reduction within voltage quality limits
D-4.6.5 Provide Peak Load reduction within voltage emergency limits
D-5 Automation of distribution operations
D-5.1 DA system updates power system model and analyzes distribution operations
D-5.1.1 Update topology model
D-5.1.2 Update facilities model
D-5.1.3 Update load model
D-5.1.4 Update relevant transmission model
D-5.1.5 Update and analyze real-time operating conditions using distribution
power flow/state estimation
D-5.1.6 Update system capacity based on real-time equipment monitoring data
D-5.1.7 Issue alarming/warning messages to the operator
D-5.1.8 Generate distribution operation reports and logs
D-5.2 DA system performs fault location, fault isolation, and service
restoration
D-5.2.1 DA indicates the faults cleared by controllable protective devices
D-5.2.1.1 Distinguish faults cleared by fuses
D-5.2.1.2 Distinguish momentary outages
D-5.2.1.3 Distinguish inrush/cold load current
D-5.2.2 DA determines the faulted sections based on SCADA fault indications and
protection lockout signals
D-5.2.3 DA estimates the probable fault locations based on SCADA fault current
measurements and real-time fault analysis
D-5.2.4 DA determines the fault-clearing non-monitored protective device based
on trouble call inputs and dynamic connectivity model
D-5.2.5 DA generates switching orders for fault isolation, service restoration,
and return to normal (taking into account the availability of remotely
controlled switching devices, feeder paralleling, and cold-load pickup)
D-5.2.5.1 Operators executes switching orders by using SCADA
D-5.2.5.2 Operator authorizes the DA application to execute the switching orders
in closed-loop mode
D-5.2.6 DA system isolates the fault and restores service automatically
by-passing the operator based on operator’s authorization in advance
D-5.2.7 DA considers creation of islands supported by distributed resources for
service restoration
D-5.3 DA system performs multi-level feeder reconfiguration for different
objectives
D-5.3.1 Service restoration
D-5.3.2 Overload elimination
D-5.3.3 Load balancing
D-5.3.4 Transmission facilities overload
D-5.3.5 Loss minimization
D-5.3.6 Voltage balancing
D-5.3.7 Reliability improvement
D-5.4 DA performs relay protection re-coordination
D-5.4.1 After feeder reconfiguration
D-5.4.2 In case of changed conditions for fuse saving
D-5.5 DA system optimally controls volt/var by changing the states of voltage
controllers, shunts, and distributed resources in a coordinated manner for
different objectives under normal and emergency conditions
D-5.5.1 Power quality improvement
D-5.5.2 Overload elimination/reduction
D-5.5.3 Load management
D-5.5.4 Transmission operation support in accordance with T&D contracts
D-5.5.5 Loss minimization in distribution and transmission
D-6 Real-time emergency operations
D-6.1 Protection equipment performs system protection actions
D-6.1.1 Fault detection, clearing, and reclosing
D-6.1.2 Under-frequency load-shedding
D-6.1.3 Under-voltage load-shedding
D-6.2 Operators manage multiple emergency alarms
D-6.2.1 Intelligent alarm processing by SCADA system
D-6.3 SCADA system performs disturbance monitoring
D-6.3.1 Fault current recording
D-6.3.2 Fault location
D-6.3.3 Event recording
D-6.4 Operators dispatch field crews to troubleshoot system and customer power
problems
D-6.4.1 Mobile radio system
D-6.4.2 Mobile computing
D-6.5 Operators perform emergency switching operations
D-6.6 Operators performs intrusive load management activities
D-6.6.1 Operators or planners identify critical loads (hospitals, etc.) ahead of
time
D-6.6.2 DA system locks out load shedding of critical loads
D-6.6.3 Operator activates direct load control
D-6.6.4 Operator activates load curtailment
D-6.6.5 Operator applies load interruption
D-6.6.6 Operators enables emergency load reduction via volt/var control
D-6.6.7 Operator applies manual rolling blackouts
D-6.7 Operator enables emergency (major event) mode of operations of operation
and maintenance personnel, and enables major event emergency mode of operation
of DA applications
D-6.8 Outage management systems collect trouble calls, generate outage
information, arrange work for trouble shooting
D-6.9 Interactive utility-customer systems inform the customers about the
progress of events
D-6.10 DA performs in major event emergency mode
D-7 Post operations
D-7.1 All systems create and archive logs and reports
D-7.2 System records voice logs of interaction between operators and field crews
D-7.3 All systems transmit reports to key parties
D-7.4 Maintenance personnel of the automated systems (DAS, OMS, WMS) performs
diagnostic analysis of system performance
D-7.5 Diagnostic analysis based on real-time equipment monitoring data, e.g.
using predictive models to determine when the equipment needs maintenance
D-8 Power system equipment maintenance
D-8.1 Maintenance staff maintain distribution equipment and lines
D-8.1.1 Maintenance staff analyzes equipment diagnostic results, compares it
with the predictive models
D-8.1.2 Maintenance staff prepares outage requests based on time and condition
criteria
D-8.1.3 Operations staff review and approve outage requests
D-8.1.4 Maintenance staff identifies assets and work crew requirements
D-8.1.5 Work crew carries out maintenance, coordinating with operators for
switching
D-8.2 Maintenance staff provides information for updating relevant databases
D-8.2.1 Work crew logs activities and results of tests
D-8.2.2 Work crew identifies assets removed and/or installed
D-8.2.3 Maintenance staff identifies errors in documentation and maps
D-8.2.4 Maintenance staff identifies marks up documentation ("red/green")
D-8.2.5 Maintenance staff indicates permanent versus temporary changes
D-9 Engineering
D-9.1 Engineering personnel perform distribution system engineering
D-9.2 Engineering personnel specifies distribution power and control equipment
D-9.3 Engineering personnel provides information for updating relevant databases
D-10 Construction management
D-10.1 Construction managers manage assets purchases
D-10.2 Construction managers plan construction projects
D-10.3 Construction managers manage crew assignments
D-10.4 Construction personnel provides information for relevant databases
D-11 Power Quality Management
D-11.1 Utility measures power quality parameters, transmits them to central
location, processes data, and stores data in PQ database in real time
D-11.2 Real time power quality state estimation system calculates power quality
characteristics based on limited monitoring information from substations,
distribution systems, and customer systems and models (pseudo-measurements)
supplementing to the needed redundancy
D-11.3 Utility exposes historical and real-time power quality data to customers
D-11.4 Utility correlates data from utility operations database, lightning
database, and other operations related database with PQ event database and
generates reports and/or stores analysis results for future reporting
D-11.5 The utility PQ evaluation system analyzes PQ events, trends, and profiles
of power quality levels of the supply system against planning limits and
operation objectives. The system is used to generate recommendations and
priorities for system improvements
D-11.6 The power quality management system analyzes PQ events and profiles to
identify causes of PQ problems and possible equipment problems that could be
corrected. Detailed recommendations are developed and automatic responses are
implemented where possible
D-11.7 The power quality information is evaluated with respect to specific
customer requirements on the specific system. Coordination with equipment and
power conditioning equipment within customer facilities is implemented to
improve productivity and reliability of customer systems. (See description in
Customer Services Domain)
D-11.8 Utility accesses PQ database and generates bill/refund/penalty statement
for events that exceed contract limits. (see description in the Customer
Services Domain)
D-11.9 Utility generates various reports from PQ database for operation,
management, engineering, and customer consumption via e-mail and web interfaces
D-12 Dispatcher Training Simulator
D-13 Distribution Asset Management
D-1 Long term distribution planning
(1 year to 5 years)
The Purpose of
Long term distribution planning (1 year to 5 years) function
is to
Develop strategic development alternatives for the distribution utility
coordinated with the expansion alternatives of regional transmission systems and
realistically possible market environment
Providing reliable service with self-healing distribution system
Standard power quality and competitive rates
directly involving
RTO/ISO
Local government entities
Major businesses
Relevant research institutions and other relevant parties
RTO expansion alternatives
Utility historic data
Local government development plans
Major business development plans
Energy conservation prospective
Distributed resources prospective
performing
Feasibility studies based on predictive simulation and optimization applications
with key interfaces between
DisCOs and TransCOs
DisCOs and RTO/ISO
Engineering and AM/FM/GIS/CIS databases within DisCo
DisCOs and DER owners
DisCOs and major customers
Utility departments within DisCOs
DisCos and local government
DisCos and area developers
DisCo and relevant research institutions and other relevant parties
with communication configuration
requirements of
WAN
LAN
Internet
with quality of service
requirements of
For DisCOs and TransCOs and DisCOs and RTO/ISO - high-volume databases including
landbases and transmission system topology
Mapping
And operational parameters
For Engineering and AM/FM/GIS databases within DisCo - high volume AM/FM/GIS
databases with detailed geographic maps displaying existing and future buildings
with security requirements of
High security due to sensitive information about area development and power
supply plans
with data management requirements
of
Geographic maps
Distribution and transmission AM/FM/GIS databases
Transmission expansion alternative databases (models)
with constraints of
Existence and comprehensiveness of applications for development of optimal
expansion plans under conditions of uncertainty in the open market environment
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
2.0 |
3.0 |
2.0 |
2.0 |
COMMENTS:
The following comments were collected during the team rating review:
Quality of Service = 2 due to data accuracy and synchronization
Significant volume of exchange data between DisCO and multiple external parties
Security =2 due to sensitive information about area development and power supply
plans
Data Management =3 due to high volume data exchange
Different data interfaces
And diverse databases
Constraints = 2 due to uncertainty of information and immature applications
D-1.1 Distribution planners
forecast loads for the long term by area
The Purpose of
Distribution planners forecast loads for the long term by area
function
is to
Determine the demand and consumption of electricity by areas with a given
resolution
Defining reasonable ranges of demand and consumption trends and distributed
resources contribution
directly involving
Utility historic data
Local government development plans
Major business development plans
Energy conservation prospective
Distributed resources prospective
performing
Alternative simulation studies
with key interfaces between
DisCOs and DER owners
Engineering and CIS databases
DisCos and area developers
DisCOs and major customers
DisCos and local government
DisCo and relevant research institutions and other relevant parties
with communication configuration
requirements of
WAN
LAN
Internet
with quality of service
requirements of
High data volume
Including detailed area maps with buildings
Communications and utility facilities
with security requirements of
High security due to sensitive information about area development and power
supply plans
with data management requirements
of
Geographic maps
Distribution and transmission AM/FM/GIS databases
Transmission expansion alternative databases (models)
with constraints of
New consumption patterns due to market impacts
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
2.0 |
3.0 |
2.0 |
1.8 |
COMMENTS:
The following comments were collected during the team rating review:
Security =2 due to sensitive information about area development and power supply
plans
Data Management =3 due to high volume data exchange
Different data interfaces
And diverse databases
Constraints = 2 due to uncertainty of information and immature applications
D-1.2 Distribution planners plan
distribution upgrades and additions in accordance with the long-term
transmission plan (using planning simulation and optimization software)
The Purpose of
Distribution planners plan distribution upgrades and additions in accordance
with the long-term transmission plan (using planning simulation and optimization
software) function
is to
Plan new T/D substations
Distribution circuits
Transformers
Distributed generation
New feeder boundaries
Var compensation means
Sectionalizing switches
Etc
directly involving
Transmission owners
RTO/ISO
DR owners
Major customers
Local government
performing
Simulation and optimization studies
with key interfaces between
DisCOs and TransCOs
DisCOs and RTO/ISO
DisCos and area developers
DisCos and local government
Engineering and AM/FM/GIS databases within DisCo
Utility departments within DisCOs
DisCo and DER
with communication configuration
requirements of
WAN
LAN
Internet
with quality of service
requirements of
High data volume
Including detailed area maps with buildings
Communications and utility facilities
with security requirements of
Limited disclosure
with data management requirements
of
Geographic maps
Distribution and transmission AM/FM/GIS databases
Transmission expansion alternative databases (models)
with constraints of
Existence and comprehensiveness of applications for development of optimal
expansion plans under conditions of uncertainty in the open market environment
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
2.0 |
3.0 |
2.0 |
2.0 |
COMMENTS:
The following comments were collected during the team rating review:
Quality of Service = 2 due to data accuracy and synchronization
Security =2 due to sensitive information about area development and power supply
plans
Data Management =3 due to high volume data exchange
Different data interfaces
And diverse databases
Constraints = 2 due to uncertainty of information and immature applications
D-1.2.1 New T/D substations
The Purpose of New
T/D substations function
is similar to function
(D-1.2) Distribution planners plan distribution upgrades and additions in
accordance with the long-term transmission plan (using planning simulation and
optimization software) above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
2.0 |
3.0 |
2.0 |
2.0 |
COMMENTS:
D-1.2.2 New distribution
circuits/conductors
The Purpose of New
distribution circuits/conductors function
is similar to function
(D-1.2) Distribution planners plan distribution upgrades and additions in
accordance with the long-term transmission plan (using planning simulation and
optimization software) above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
2.0 |
3.0 |
2.0 |
2.0 |
COMMENTS:
D-1.2.3 New distribution
transformers
The Purpose of New
distribution transformers function
is similar to function
(D-1.2) Distribution planners plan distribution upgrades and additions in
accordance with the long-term transmission plan (using planning simulation and
optimization software) above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
2.0 |
3.0 |
2.0 |
2.0 |
COMMENTS:
D-1.2.4 New distributed generation,
including distributed resources impact studies
The Purpose of New
distributed generation, including distributed resources impact studies
function
is similar to function
(D-1.2) Distribution planners plan distribution upgrades and additions in
accordance with the long-term transmission plan (using planning simulation and
optimization software) above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
2.0 |
3.0 |
2.0 |
2.0 |
COMMENTS:
D-1.2.4.1 DisCo plans utility-owned
DR to meet reliability and power quality targets
The Purpose of DisCo
plans utility-owned DR to meet reliability and power quality targets
function
is similar to function
(D-1.2.4) New distributed generation, including distributed resources impact
studies above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
2.0 |
3.0 |
2.0 |
2.0 |
COMMENTS:
D-1.2.4.2 DisCo acquires DR base
information (to provide ratings and device models)
The Purpose of DisCo
acquires DR base information (to provide ratings and device models)
function
is similar to function
(D-1.2.4) New distributed generation, including distributed resources impact
studies above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
2.0 |
3.0 |
2.0 |
2.0 |
COMMENTS:
D-1.2.4.3 DisCo analyzes DR
interconnection to the power system
The Purpose of DisCo
analyzes DR interconnection to the power system function
is similar to function
(D-1.2.4) New distributed generation, including distributed resources impact
studies above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
2.0 |
3.0 |
2.0 |
2.0 |
COMMENTS:
D-1.2.5 New circuit boundaries
The Purpose of New
circuit boundaries function
is similar to function
(D-1.2) Distribution planners plan distribution upgrades and additions in
accordance with the long-term transmission plan (using planning simulation and
optimization software) above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
2.0 |
3.0 |
2.0 |
2.0 |
COMMENTS:
D-1.2.6 New switch allocation
The Purpose of New
switch allocation function
is similar to function
(D-1.2) Distribution planners plan distribution upgrades and additions in
accordance with the long-term transmission plan (using planning simulation and
optimization software) above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
2.0 |
3.0 |
2.0 |
2.0 |
COMMENTS:
D-1.2.7 New capacitor allocation
The Purpose of New
capacitor allocation function
is similar to function
(D-1.2) Distribution planners plan distribution upgrades and additions in
accordance with the long-term transmission plan (using planning simulation and
optimization software) above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
2.0 |
3.0 |
2.0 |
2.0 |
COMMENTS:
D-1.3 Distribution planners plan
distribution automation
The Purpose of
Distribution planners plan distribution automation function
is to include distribution automation in the standard
procedures of planning and procurement in conjunction with the long-term plans
of distribution system development in order to benefit from distribution
automation in the most efficient way
directly involving
Planning
Operation
And IT departments of the utility
Automation plans (requirements) of transmission owners and RTO/ISO
performing
Simulation and optimization studies for the alternative expansion scenarios
with key interfaces between
DisCOs and TransCOs
DisCOs and RTO/ISO
with communication configuration
requirements of
WAN
LAN
Internet
with quality of service
requirements of
Low data volume
with security requirements of
Limited disclosure
with data management requirements
of
Large distribution system model with layers of alternative expansions
Storage
with constraints of
Legacy of planning procedures and immaturity of relevant applications
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
1.0 |
1.0 |
3.0 |
2.0 |
1.4 |
COMMENTS:
The following comments were collected during the team rating review:
Data Management =3
Due to high volume data for existing and future models
Data storage
Constraints = 2 due to immature applications ( no optimization and coordination)
D-1.3.1 SCADA
The Purpose of SCADA
function
is similar to function
(D-1.3) Distribution planners plan distribution automation above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
1.0 |
1.0 |
3.0 |
2.0 |
1.4 |
COMMENTS:
D-1.3.2 DA functions
The Purpose of DA
functions function
is similar to function
(D-1.3) Distribution planners plan distribution automation above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
1.0 |
1.0 |
3.0 |
2.0 |
1.4 |
COMMENTS:
D-1.3.2.1 Fault Location
The Purpose of Fault
Location function
is similar to function
(D-1.3.2) DA functions above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
1.0 |
1.0 |
3.0 |
2.0 |
1.4 |
COMMENTS:
D-1.3.2.2 Fault isolation and
service restoration
The Purpose of Fault
isolation and service restoration function
is similar to function
(D-1.3.2) DA functions above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
1.0 |
1.0 |
3.0 |
2.0 |
1.4 |
COMMENTS:
D-1.3.2.3 Outage statistics
calculations
The Purpose of
Outage statistics calculations function
is similar to function
(D-1.3.2) DA functions above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
1.0 |
1.0 |
3.0 |
2.0 |
1.4 |
COMMENTS:
D-1.3.2.4 Volt/Var control
The Purpose of
Volt/Var control function
is similar to function
(D-1.3.2) DA functions above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
1.0 |
1.0 |
3.0 |
2.0 |
1.4 |
COMMENTS:
D-1.3.2.5 Planned outage management
The Purpose of
Planned outage management function
is similar to function
(D-1.3.2) DA functions above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely to
involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
1.0 |
1.0 |
3.0 |
2.0 |
1.4 |
COMMENTS:
D-1.3.2.6 Feeder reconfiguration
The Purpose of
Feeder reconfiguration function
is similar to function
(D-1.3.2) DA functions above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
1.0 |
1.0 |
3.0 |
2.0 |
1.4 |
COMMENTS:
D-1.3.2.7 Cold load pickup
The Purpose of Cold
load pickup function
is similar to function
(D-1.3.2) DA functions above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
1.0 |
1.0 |
3.0 |
2.0 |
1.4 |
COMMENTS:
D-1.3.2.8 Dynamic limit
calculations
The Purpose of
Dynamic limit calculations function
is similar to function
(D-1.3.2) DA functions above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
1.0 |
1.0 |
3.0 |
2.0 |
1.4 |
COMMENTS:
D-1.3.2.9 Feeder paralleling
The Purpose of
Feeder paralleling function
is similar to function
(D-1.3.2) DA functions above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
1.0 |
1.0 |
3.0 |
2.0 |
1.4 |
COMMENTS:
D-1.3.2.10 Integration with EMS/MOS
The Purpose of
Integration with EMS/MOS function
is similar to function
(D-1.3.2) DA functions above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
1.0 |
1.0 |
3.0 |
2.0 |
1.4 |
COMMENTS:
D-1.3.2.11 Equipment monitoring and
diagnostics
The Purpose of
Equipment monitoring and diagnostics function
is similar to function
(D-1.3.2) DA functions above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
1.0 |
1.0 |
3.0 |
2.0 |
1.4 |
COMMENTS:
D-1.3.2.12 Other
The Purpose of Other
function
is similar to function
(D-1.3.2) DA functions above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
1.0 |
1.0 |
3.0 |
2.0 |
1.4 |
COMMENTS:
D-1.4 Distribution planners prepare
long-term contracts with transmission companies covering mutual obligations for
the T&D interfaces, operation coordination, and information exchange
The Purpose of
Distribution planners prepare long-term contracts with transmission companies
covering mutual obligations for the T&D interfaces, operation coordination, and
information exchange function
is to include in the planning process the possible
alternative conditions of the T&D interfaces and select the most efficient
combination of distribution facility upgrades and contractual obligations
between D&T
directly involving
DIsCo and TransCo
performing
Simulation and optimization studies
with key interfaces between
DisCOs and TransCo
with communication configuration
requirements of
WAN
LAN
with quality of service
requirements of
Low volume and speed of data exchange
with security requirements of
Limited disclosure
with data management requirements
of
Large distribution system model with layers of alternative expansions
with constraints of
Legacy of planning procedures and immaturity of relevant applications
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
1.0 |
1.0 |
3.0 |
2.0 |
1.4 |
COMMENTS:
The following comments were collected during the team rating review:
Data Management =3
Due to high volume data for existing and future models
Constraints = 2 due to immature applications ( no optimization and coordination)
D-1.5 Distribution planners prepare
long-term contracts with generators connected to distribution
The Purpose of
Distribution planners prepare long-term contracts with generators connected
to distribution function
is to include in the planning process the possible alternative
conditions of the D&DR interfaces and select the most efficient combination of
distribution facility upgrades and contractual obligations between D&DR
directly involving
DIsCo and DR
performing
Simulation
Impact
And optimization studies
with key interfaces between
DisCOs and DER owners
with communication configuration
requirements of
WAN
LAN
Internet
with quality of service
requirements of
Low volume and low speed of data exchange
with security requirements of
Limited disclosure
with data management requirements
of
Large distribution system model with layers of alternative expansions
with constraints of
Legacy of planning procedures and immaturity of relevant applications
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
1.0 |
1.0 |
3.0 |
2.0 |
1.4 |
COMMENTS:
The following comments were collected during the team rating review:
Data Management =3
Due to high volume data for existing and future models
Constraints = 2 due to immature applications ( no optimization and coordination)
D-1.6 Distribution planners prepare
long-term contract with customers regarding service reliability and power
quality
The Purpose of
Distribution planners prepare long-term contract with customers regarding
service reliability and power quality function
is to
Include in the planning process the possible alternative conditions of the
DisCO&Customer interfaces and relationships and select the most efficient
combination of distribution facility upgrades and contractual obligations
between DisCO and major customers regarding load management
Reliability
Power quality
Var compensation
Etc
directly involving
DIsCo and major customers
performing
Simulation
Impact
And optimization studies
with key interfaces between
DisCOs and major customers
with communication configuration
requirements of
WAN
LAN
Internet
with quality of service
requirements of
Low volume and low speed of data exchange
with security requirements of
Limited disclosure
with data management requirements
of
Large distribution system model with layers of alternative expansions
with constraints of
Legacy of planning procedures and immaturity of relevant applications
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
3.0 |
2.0 |
1.6 |
COMMENTS:
The following comments were collected during the team rating review:
Data Management =3
Due to high volume data for existing and future models
Constraints = 2 due to immature applications ( no optimization and coordination)
D-1.7 Distribution planners
generate requirements for information support of distribution domain activities
The Purpose of
Distribution planners generate requirements for information support of
distribution domain activities function
is to prepare the system models of the future for the
information support of the planned distribution operation processes
directly involving
Planning
Operation
And IT departments of the utility
Distribution expansion and automation plans
performing
Information model specifications
with key interfaces between
DisCOs and utility departments
with communication configuration
requirements of
LAN
with quality of service
requirements of
Low value and low speed of external information flows
with security requirements of
Limited disclosure
with data management requirements
of
Low level
with constraints of
Legacy of planning procedures
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
0.0 |
1.0 |
0.8 |
COMMENTS:
D-1.8 Distribution planners update
the future layers of relevant databases
The Purpose of
Distribution planners update the future layers of relevant databases
function
is to populate the future distribution model based on
planning decisions
directly involving
Planning
Operation
And IT departments of the utility
Distribution expansion and automation plans
performing
Update of AM/FM/GIS and Asset Management databases
Data consistency checking
Error corrections
with key interfaces between
Utility departments within DisCOs
Engineering and AM/FM/GIS/CIS databases
with communication configuration
requirements of
LAN
with quality of service
requirements of
Low value and low speed of external information flows
with security requirements of
Limited disclosure
with data management requirements
of
Average volume of incremental data
with constraints of
Legacy of database support
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
COMMENTS:
D-2 Short-term distribution
planning (1 week to 1 year)
The Purpose of
Short-term distribution planning (1 week to 1 year) function
is to
Update circuit boundaries
Switch placement
Capacitor placement
No-load tap positions
Phase load allocation
Controller and DA application settings
Contracts with other parties
Conduct DER impact studies
Issue permits for constructions
Prepare maintenance plans
And update databases
Providing reliable service with self-healing distribution system
Standard power quality and competitive rates
directly involving
Short-term load forecasts
Builder requests
Work
Maintenance requests
performing
Simulation and optimization studies
with key interfaces between
Engineering and AM/FM/GIS and CIS databases within DisCo
DisCOs and DER owners
DisCos and customer representatives (serving entities)
DisCos and area developers
DisCOs and TransCOs
Within DisCo's departments
DisCOs and RTO/ISO
DisCos and customers
DisCos and contractors
with communication configuration
requirements of
WAN
LAN
Internet
with quality of service
requirements of
Low volume data exchange
With somehow flexible timeframes
with security requirements of
Information exchange is limited to relevant parties due to sensitive information
about area development and power supply plans
with data management requirements
of
Geographic maps
Distribution and transmission AM/FM/GIS and CIS databases for internal use by
utility departments
with constraints of
Existence and comprehensiveness of applications for development of optimal
short-term plans under conditions of uncertainty in the open market environment
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
2.0 |
3.0 |
2.0 |
2.0 |
COMMENTS:
The following comments were collected during the team rating review:
Quality of service = 2 due to data accuracy and synchronization
Significant volume of exchange data between DisCO and multiple external parties
Security =2 due to sensitive information about area development and power supply
plans
Data Management =3
Due to high volume data exchange
Archive data
Unique interfaces
And diverse database structures
Constraints = 2 due to uncertainty of information and immature applications
D-2.1 Short-term load forecast
The Purpose of
Short-term load forecast function
is to update the demand and consumption forecast based on the
latest available information
directly involving
Utility historic data
New development schedules
Major business predictions
Energy conservation actions
Distributed resources schedules
performing
Load forecast for existing nodal loads
Forecast of allocation and amount of new loads
Forecast/scheduling of distributed resources
with key interfaces between
Engineering and AM/FM/GIS and CIS databases within DisCo
DisCOs and DER owners
DisCos and major customers
DisCos and customer representatives (serving entities)
DisCos and area developers
with communication configuration
requirements of
WAN
LAN
Internet
with quality of service
requirements of
Low volume of external data exchange
With somehow flexible timeframes
with security requirements of
Information exchange is limited to relevant parties due to sensitive information
about area development and power supply plans
with data management requirements
of
Geographic maps
Distribution and transmission AM/FM/GIS and CIS databases for internal use by
utility departments
with constraints of
Existence and comprehensiveness of applications for development of optimal
short-term plans under conditions of uncertainty in the open market environment
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
2.0 |
3.0 |
2.0 |
1.8 |
COMMENTS:
The following comments were collected during the team rating review:
Security =2 due to sensitive information about area development and power supply
plans
Data Management =3
Due to high volume data exchange
Archive data
Unique interfaces
And diverse database structures
Constraints = 2 due to uncertainty of information and immature applications
D-2.1.1 Load forecast for existing
nodal loads
The Purpose of Load
forecast for existing nodal loads function
is similar to function
(D-2.1) Short-term load forecast above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
2.0 |
3.0 |
2.0 |
1.8 |
COMMENTS:
D-2.1.2 Forecast of allocation and
amount of new loads
The Purpose of
Forecast of allocation and amount of new loads function
is similar to function
(D-2.1) Short-term load forecast above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
2.0 |
3.0 |
2.0 |
1.8 |
COMMENTS:
D-2.1.3 Forecast/scheduling of
distributed resources
The Purpose of
Forecast/scheduling of distributed resources function
is similar to function
(D-2.1) Short-term load forecast above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
2.0 |
3.0 |
2.0 |
1.8 |
COMMENTS:
D-2.2 Update of circuit boundaries
The Purpose of
Update of circuit boundaries function
is to
Enhance reliability
Power quality
Utilization of distribution facilities
And operational efficiency based on the latest load and facility data by
adjusting the operating parameters not controllable in real time
directly involving
Planning
Operation
Engineering departments of the utility
performing
Multi-level feeder reconfiguration studies based on multiple criteria
coordinated with other optimization planning studies
with key interfaces between
DisCOs and TransCOs
Engineering and AM/FM/GIS and CIS databases within DisCo
DisCOs and DER owners
DisCos and major customers
DisCos and customer representatives (serving entities)
with communication configuration
requirements of
WAN
LAN
Internet
with quality of service
requirements of
Low volume of external data exchange
With somehow flexible timeframes
with data management requirements
of
Geographic maps
Distribution and transmission AM/FM/GIS and CIS databases for internal use by
utility departments
with constraints of
Existence and comprehensiveness of applications for development of optimal
short-term plans under conditions of uncertainty in the open market environment
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
2.0 |
3.0 |
2.0 |
1.8 |
COMMENTS:
The following comments were collected during the team rating review:
Security =2 due to sensitive information about area development and power supply
plans
Data Management =3
Due to high volume data exchange
Archive data
Unique interfaces
And diverse database structures
Constraints = 2 due to uncertainty of information and immature applications
D-2.3 Update of switch placement
The Purpose of
Update of switch placement function
is to
Enhance reliability
Power quality
Utilization of distribution facilities
And operational efficiency based on the latest load and facility data by
adjusting the operating parameters not controllable in real time
directly involving
Planning
Operation
Engineering departments of the utility
performing
Predictive reliability assessment and sectionalizing optimization coordinated
with other planning optimization functions
with key interfaces between
DisCOs and TransCOs
Planning and AM/FM/GIS and CIS databases within DisCo
DisCOs and DER owners
DisCos and major customers
DisCos and customer representatives (serving entities)
DisCos and area developers
with communication configuration
requirements of
WAN
LAN
Internet
with quality of service
requirements of
Low volume of external data exchange
With somehow flexible timeframes
with data management requirements
of
Geographic maps
Distribution and transmission AM/FM/GIS and CIS databases for internal use by
utility departments
with constraints of
Existence and comprehensiveness of applications for development of optimal
short-term plans under conditions of uncertainty in the open market environment
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
2.0 |
3.0 |
2.0 |
1.8 |
COMMENTS:
The following comments were collected during the team rating review:
Security =2 due to sensitive information about area development and power supply
plans
Data Management =3
Due to high volume data exchange
Archive data
Unique interfaces
And diverse database structures
Constraints = 2 due to uncertainty of information and immature applications
D-2.4 Update of capacitor placement
and sizing
The Purpose of
Update of capacitor placement and sizing function
is to
Enhance reliability
Power quality
Utilization of distribution facilities
And operational efficiency based on the latest load and facility data by
adjusting the operating parameters not controllable in real time
directly involving
Planning
Operation
Engineering departments of the utility
performing
Multi-objective feeder capacitor optimization coordinated with other planning
optimization functions
with key interfaces between
DisCOs and TransCOs
Planning and AM/FM/GIS and CIS databases within DisCo
DisCOs and DER owners
DisCos and major customers
DisCos and customer representatives (serving entities)
DisCos and area developers
with communication configuration
requirements of
WAN
LAN
Internet
with quality of service
requirements of
Low volume of external data exchange
With somehow flexible timeframes
with data management requirements
of
Geographic maps
Distribution and transmission AM/FM/GIS and CIS databases for internal use by
utility departments
with constraints of
Existence and comprehensiveness of applications for development of optimal
short-term plans under conditions of uncertainty in the open market environment
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
2.0 |
3.0 |
2.0 |
1.8 |
COMMENTS:
The following comments were collected during the team rating review:
Security =2 due to sensitive information about area development and power supply
plans
Data Management =3
Due to high volume data exchange
Archive data
Unique interfaces
And diverse database structures
Constraints = 2 due to uncertainty of information and immature applications
D-2.5 Update of no-load tap
positions
The Purpose of
Update of no-load tap positions function
is to
Enhance reliability
Power quality
Utilization of distribution facilities
And operational efficiency based on the latest load and facility data by
adjusting the operating parameters not controllable in real time
directly involving
Planning
Operation
Engineering departments of the utility
performing
Multi-objective no-load tap position optimization coordinated with the
capabilities of real-time multi-criteria volt-var control coordinated with other
planning optimization functions
with key interfaces between
DisCOs and TransCOs
Planning and AM/FM/GIS and CIS databases within DisCo
DisCOs and DER owners
DisCos and major customers
DisCos and customer representatives (serving entities)
DisCos and area developers
with communication configuration
requirements of
WAN
LAN
Internet
with quality of service
requirements of
Low volume of external data exchange
With somehow flexible timeframes
with data management requirements
of
Geographic maps
Distribution and transmission AM/FM/GIS and CIS databases for internal use by
utility departments
with constraints of
Existence and comprehensiveness of applications for development of optimal
short-term plans under conditions of uncertainty in the open market environment
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
2.0 |
3.0 |
2.0 |
1.8 |
COMMENTS:
The following comments were collected during the team rating review:
Security =2 due to sensitive information about area development and power supply
plans
Data Management =3
Due to high volume data exchange
Archive data
Unique interfaces
And diverse database structures
Constraints = 2 due to uncertainty of information and immature applications
D-2.6 Update phase load allocation
for better load and voltage balancing
The Purpose of
Update phase load allocation for better load and voltage balancing
function
is to
Enhance reliability
Power quality
Utilization of distribution facilities
And operational efficiency based on the latest load and facility data by
adjusting the operating parameters not controllable in real time
directly involving
Planning
Operation
Engineering departments of the utility
performing
Phase loading optimization for the planning time frame coordinated with other
planning optimization functions
with key interfaces between
Planning and AM/FM/GIS and CIS databases within DisCo
DisCOs and DER owners
DisCos and major customers
DisCos and customer representatives (serving entities)
with communication configuration
requirements of
WAN
LAN
Internet
with quality of service
requirements of
Low volume of external data exchange
With somehow flexible timeframes
with data management requirements
of
Geographic maps
Distribution and transmission AM/FM/GIS and CIS databases for internal use by
utility departments
with constraints of
Existence and comprehensiveness of applications for optimum load and voltage
balancing due to uncertainty of the load forecast on per phase basis
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
2.0 |
3.0 |
2.0 |
1.8 |
COMMENTS:
The following comments were collected during the team rating review:
Security =2 due to sensitive information about area development and power supply
plans
Data Management =3
Due to high volume data exchange
Archive data
Unique interfaces
And diverse database structures
Constraints = 2 due to uncertainty of information and immature applications
D-2.7 Update of contracts with
transmission company
The Purpose of
Update of contracts with transmission company function
is to
Adjust the contractual agreements to the latest available information
Based on the updated planned operating conditions and new information from other
parties
directly involving
Planning
Operation
Engineering departments of the utility
TransCos
performing
Simulation and optimization studies of the alternative operational parameters in
the DisCO-TransCO interfaces
with key interfaces between
DisCos and TransCo
with communication configuration
requirements of
WAN
LAN
Internet
with quality of service
requirements of
Low volume data exchange between external parties
with security requirements of
Limited disclosure
with data management requirements
of
Large distribution system model
with constraints of
Legacy of planning procedures and immaturity of relevant applications
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
1.0 |
1.0 |
3.0 |
2.0 |
1.4 |
COMMENTS:
The following comments were collected during the team rating review:
Data Management =3
Due to high volume data for existing and future models
Constraints = 2 due to immature applications ( no optimization and coordination)
D-2.8 Update of automation settings
The Purpose of
Update of automation settings function
is to
Adjust the relay protection settings and coordination
Load shedding amount
Its number and settings of groups
Distribution automation tuning parameters in accordance with the updated plans
directly involving
Planning
Operation
Engineering
Relay protection departments of the utility
TransCos
ISO/RTO
DER
Major customers
performing
Contingency analysis and relay coordination studies
with key interfaces between
Within DisCo's departments
DisCO and RTO/ISO
DisCo and TransCOs
DisCOs and DER owners
DisCos and major customers
DisCos and customer representatives (serving entities)
with communication configuration
requirements of
WAN
LAN
Internet
with quality of service
requirements of
Low volume of external data exchange
with security requirements of
Limited disclosure
with data management requirements
of
Large distribution AM/FM databases
Transmission equivalents
DER and major customer parameters
with constraints of
Immature applications for complex distribution systems with multiple DERs
Looped circuits
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
2.0 |
2.0 |
1.4 |
COMMENTS:
The following comments were collected during the team rating review:
Data Management =2 due to high volume data for distribution models
Constraints = 2 due to immature applications
D-2.9 Short-term distributed
resources impact studies
The Purpose of
Short-term distributed resources impact studies function
is to determine the requirements for connection of a new DER
directly involving
DisCo planning
Relaying
And operation departments
DER owners
performing
Simulation and optimization studies
with key interfaces between
DisCos and DER owners
with communication configuration
requirements of
LAN
Internet
with quality of service
requirements of
Accurate data from DER owners
Limited time for DisCo response (about 2 weeks)
with security requirements of
Limited disclosure
with data management requirements
of
Large distribution models synchronized with the time of requested connection and
later
with constraints of
Comprehensiveness of applications
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
3.0 |
2.0 |
1.6 |
COMMENTS:
The following comments were collected during the team rating review:
Data Management =3 due to high volume data for distribution models
Synchronization with the required time frame, which may be different for
different DERs
Constraints = 2 due to immature applications
D-2.10 Update of contracts with
distribution generators
The Purpose of
Update of contracts with distribution generators function
is to
Adjust the contractual agreements to the latest available information
Based on the updated planned operating conditions and new information from other
parties
directly involving
Planning
Operation
Engineering departments of the utility
DER owners
performing
Simulation and optimization studies of the alternative operational parameters in
the DisCO-DER interfaces
with key interfaces between
DisCos and DER owners
with communication configuration
requirements of
LAN
Internet
with quality of service
requirements of
Low volume data exchange between external parties
with security requirements of
Limited disclosure
with data management requirements
of
Large distribution system model
Localized around the DER's locations
with constraints of
Legacy of planning procedures and immaturity of relevant applications
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
1.0 |
1.0 |
2.0 |
2.0 |
1.2 |
COMMENTS:
The following comments were collected during the team rating review:
Data Management =2
Due to high volume data for distribution models
Constraints = 2 due to immature applications ( no optimization and coordination)
The rating for Data Management does not match the comment. --
Peter Sanza - 05 Apr
2003
D-2.11 Update of contracts with
customers
The Purpose of
Update of contracts with customers function
is to
Adjust the contractual agreements to the latest available information
Based on the updated planned operating conditions and new information from other
parties
directly involving
Planning
Operation
Engineering departments of the utility
Major customers
Customer representatives
performing
Simulation and optimization studies of the alternative operational parameters in
the DisCO-customer interfaces
Load management studies
Power quality studies
with key interfaces between
DisCos and major customers
DisCos and customer representatives (serving entities)
with communication configuration
requirements of
LAN
Internet
with quality of service
requirements of
Average volume data exchange between external parties
with security requirements of
Limited disclosure
with data management requirements
of
Large distribution system model
Localized around the major customer locations
with constraints of
Legacy of planning procedures and immaturity of relevant applications
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
2.0 |
1.0 |
3.0 |
2.0 |
1.6 |
COMMENTS:
The following comments were collected during the team rating review:
Quality of service = 2 due to significant volume of exchange data between DisCO
and multiple external parties
Data Management =3
Due to high volume data for distribution models
Average volume data for external parties
And diverse nature of data
Constraints = 2 due to immature applications ( no optimization and coordination)
D-2.12 Contractor /Builder requests
new service connection (see IEC WG14 Use Case #2 and 3)
The Purpose of
Contractor /Builder requests new service connection (see IEC WG14 Use Case #2
and 3) function
is to determine the requirements for connection of a new major
service connection
directly involving
DisCo planning
Relaying
And operation departments
Contractor/Builder/customer
performing
Simulation and optimization studies
with key interfaces between
DisCos and customers
DisCos and contractor
with communication configuration
requirements of
LAN
Internet
with quality of service
requirements of
Accurate data from builders
Limited time for DisCo response
with security requirements of
Limited disclosure
with data management requirements
of
Large distribution models synchronized with the time of requested connection and
later
with constraints of
Comprehensiveness of applications
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
3.0 |
2.0 |
1.6 |
COMMENTS:
The following comments were collected during the team rating review:
Data Management =3 due to high volume data for distribution models
Synchronization with the required time frame, which may be different for
different constructions
Constraints = 2 due to immature applications
D-2.13 Update of relevant databases
The Purpose of
Update of relevant databases function
is to populate the future distribution model based on updated
planning decisions
directly involving
Planning
Operation
And IT departments of the utility
performing
Update of AM/FM/GIS
Asset Management and other relevant databases
Data consistency checking
Error corrections
with key interfaces between
DisCos and utility departments
with communication configuration
requirements of
LAN
with quality of service
requirements of
Low volume and low speed of external information flows
with security requirements of
Limited disclosure
with data management requirements
of
Average volume of incremental data
with constraints of
Legacy of database support
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
COMMENTS:
D-2.14 Prepare maintenance plan
The Purpose of
Prepare maintenance plan function
is to
Calculate system utilization based on forecast load and nameplate ratings
Schedule maintenance operations
Schedule equipment replacement
directly involving
Operation
Planning
Maintenance
IT departments of the utility
performing
Diagnostic analysis
Scheduling
Simulation
And optimization studies
with key interfaces between
DisCos and utility departments
DisCos and major customers
DisCos and DER owners
with communication configuration
requirements of
LAN
Internet
with quality of service
requirements of
Low volume and low speed of external information flows
with security requirements of
Limited disclosure
with data management requirements
of
Large distribution models synchronized with the time of requested maintenance
with constraints of
Comprehensiveness of applications
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
0.0 |
1.0 |
3.0 |
2.0 |
1.2 |
COMMENTS:
The following comments were collected during the team rating review:
Data Management =3 due to high volume data for distribution models
Synchronization with the required time frame, which may be different for
different constructions
Constraints = 2 due to immature applications
D-2.14.1 Calculate system
utilization based on forecast load and nameplate ratings
The Purpose of
Calculate system utilization based on forecast load and nameplate ratings
function
is similar to function
(D-2.14) Prepare maintenance plan above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
0.0 |
1.0 |
3.0 |
2.0 |
1.2 |
COMMENTS:
D-2.14.2 Schedule maintenance
operations - time-based
The Purpose of
Schedule maintenance operations - time-based function
is similar to function
(D-2.14) Prepare maintenance plan above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
0.0 |
1.0 |
3.0 |
2.0 |
1.2 |
COMMENTS:
D-2.14.3 Schedule maintenance
operations - predictive, based on data and models
The Purpose of
Schedule maintenance operations - predictive, based on data and models
function
is similar to function
(D-2.14) Prepare maintenance plan above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
0.0 |
1.0 |
3.0 |
2.0 |
1.2 |
COMMENTS:
D-2.14.4 Schedule equipment
replacement - based on age of equipment
The Purpose of
Schedule equipment replacement - based on age of equipment
function
is similar to function
(D-2.14) Prepare maintenance plan above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
0.0 |
1.0 |
3.0 |
2.0 |
1.2 |
COMMENTS:
D-2.14.5 Schedule equipment
replacement - predictive, based on data and models
The Purpose of
Schedule equipment replacement - predictive, based on data and models
function
is similar to function
(D-2.14) Prepare maintenance plan above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
0.0 |
1.0 |
3.0 |
2.0 |
1.2 |
COMMENTS:
D-2.14.6 Schedule equipment
replacement - based on contingency scenarios
The Purpose of
Schedule equipment replacement - based on contingency scenarios
function
is similar to function
(D-2.14) Prepare maintenance plan above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
0.0 |
1.0 |
3.0 |
2.0 |
1.2 |
COMMENTS:
D-2.14.7 Schedule spare
distribution, ensure sufficient at each site
The Purpose of
Schedule spare distribution, ensure sufficient at each site
function
is similar to function
(D-2.14) Prepare maintenance plan above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
0.0 |
1.0 |
3.0 |
2.0 |
1.2 |
COMMENTS:
D-3 Operational planning (1 day to
1 week ahead)
The Purpose of
Operational planning (1 day to 1 week ahead) function
is to
Optimally prepare the short-term operating conditions of the distribution system
Providing reliable service with self-healing distribution system
Standard power quality and competitive rates
directly involving
Short-term load forecasts
Information about on-going maintenance
Short-term outage requests
Real-time and nominal databases
performing
Simulation and optimization studies for the look-ahead time interval
with key interfaces between
Operation and Work management departments of DisCo
Within DisCo's departments
DisCo and contractor
DisCos and field crews
DisCos and customers
DisCos and weather system
DisCos and security institutions
DisCOs and TransCOs
DisCOs and RTO/ISO
Engineering and AM/FM/GIS databases within DisCo
DisCOs and DER owners
DisCos and major customers
DisCos and customer representatives (serving entities)
Operation planning databases and real-time databases
Operation planning databases and work management databases
with communication configuration
requirements of
WAN
LAN
Internet
with quality of service
requirements of
High availability and accuracy
Several times a day with due times
with security requirements of
Moderate security
with data management requirements
of
Geographic maps
Distribution and transmission AM/FM/GIS and CIS databases for internal use by
utility departments
with constraints of
Existence and comprehensiveness of applications for development of optimal
operation plans under conditions of uncertainty in the open market environment
Necessity of taking into account coordination of different distribution
operation processes (reconfiguration
Volt/var control
DER re-dispatch
Relay protection re-coordination)
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
3.0 |
3.0 |
2.4 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration = 2 due to diversity of multiple communications
Quality of Service =2 due to accuracy and clarity requirements
Security =2 due to planning for major events including terror alarm conditions
Data Management =3
Due to high volume data model for look-ahead studies
Constraints = 3 due to immature applications ( no optimization and coordination)
D-3.1 Planned outage management by
using DA applications in study/look-ahead mode and DA databases
The Purpose of
Planned outage management by using DA applications in study/look-ahead mode and
DA databases function
is to
Optimally arrange the planned outages based on the latest prediction of the
operating conditions based on DisCO
TransCo
ISO/RTO
MOS information
Maximizing the reliability of service and power quality
directly involving
Operation planners
Maintenance department
performing
Analyses of expected loads
Transmission maintenance
Transmission operation support
ISO/RTO load management requirements
Ongoing maintenance in distribution
New outage request analyses and scheduling
Multi-level feeder reconfiguration
Contingency analysis
Reliability assessment
DER rescheduling
Relay protection re-coordination
And switching order creation
with key interfaces between
Operation and Work management departments of DisCo
DisCos and TransCo
DisCos and ISO/RTO
DisCos and DER owners
DisCos and major customers
DisCos and customer representatives (serving entities)
Operation planning databases and real-time databases
with communication configuration
requirements of
WAN
LAN
Internet
with quality of service
requirements of
Low volume of external exchanges
High accuracy of data
Timely response
with security requirements of
Moderate security
with data management requirements
of
Geographic maps
Distribution and transmission AM/FM/GIS and CIS databases for internal use by
utility departments
with constraints of
Existence and comprehensiveness of applications for development of optimal
operation plans under conditions of uncertainty in the open market environment
Necessity of taking into account coordination of different distribution
operation processes (reconfiguration
Volt/var control
DER re-dispatch
Relay protection re-coordination)
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
1.0 |
3.0 |
3.0 |
2.0 |
COMMENTS:
The following comments were collected during the team rating review:
Quality of Service =2 due to accuracy requirements
Data Management =3
Due to high volume data model for look-ahead studies
Constraints = 3 due to immature applications ( no optimization and coordination)
D-3.1.1 Outage request analysis and
scheduling, taking into account the capabilities of real-time DA functions
The Purpose of
Outage request analysis and scheduling, taking into account the capabilities of
real-time DA functions function
is similar to function
(D-3.1) Planned outage management by using DA applications in study/look-ahead
mode and DA databases above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
1.0 |
3.0 |
3.0 |
2.0 |
COMMENTS:
D-3.1.2 Planners/operators perform
load analysis of substation equipment based on data
The Purpose of
Planners/operators perform load analysis of substation equipment based on data
function
is similar to function
(D-3.1) Planned outage management by using DA applications in study/look-ahead
mode and DA databases above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
1.0 |
3.0 |
3.0 |
2.0 |
COMMENTS:
D-3.1.3 Multi-level feeder
reconfiguration
The Purpose of
Multi-level feeder reconfiguration function
is similar to function
(D-3.1) Planned outage management by using DA applications in study/look-ahead
mode and DA databases above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
1.0 |
3.0 |
3.0 |
2.0 |
COMMENTS:
D-3.1.4 Contingency
analysis/reliability (risk) assessment
The Purpose of
Contingency analysis/reliability (risk) assessment function
is similar to function
(D-3.1) Planned outage management by using DA applications in study/look-ahead
mode and DA databases above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
1.0 |
3.0 |
3.0 |
2.0 |
COMMENTS:
D-3.1.5 Distributed resources
re-scheduling
The Purpose of
Distributed resources re-scheduling function
is similar to function
(D-3.1) Planned outage management by using DA applications in study/look-ahead
mode and DA databases above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
1.0 |
3.0 |
3.0 |
2.0 |
COMMENTS:
D-3.1.6 Protection coordination
analysis
The Purpose of
Protection coordination analysis function
is similar to function
(D-3.1) Planned outage management by using DA applications in study/look-ahead
mode and DA databases above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
1.0 |
3.0 |
3.0 |
2.0 |
COMMENTS:
D-3.1.7 Switching order generation
for facilitating the planned outages and for return to normal
The Purpose of
Switching order generation for facilitating the planned outages and for return
to normal function
is similar to function
(D-3.1) Planned outage management by using DA applications in study/look-ahead
mode and DA databases above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
1.0 |
3.0 |
3.0 |
2.0 |
COMMENTS:
D-3.2 Work management (planning
stage)
The Purpose of Work
management (planning stage) function
is to
Authorize scheduled work
Schedule work crews for authorized work
Identify assets required for the work
Design/plan work site for safety
Prepare working and switching orders
directly involving
Work management
Maintenance
Operation departments
And utility and contractor's field crews
performing
Verification of work and switching orders
Preparing work permits
Verifying conditions for recall of work
If needed
with key interfaces between
Within DisCo's departments
DisCo and contractor
DisCos and field crews
Engineering and AM/FM/GIS databases within DisCo
Operation planning databases and work management databases
with communication configuration
requirements of
LAN
Internet
Mobile communications
with quality of service
requirements of
High accuracy and clarity of operational and safety related information
with security requirements of
Limited disclosure
with data management requirements
of
Drawing and maps transmitted over mobile communications
Sufficient time for verification of transmittal
with constraints of
Legacy procedures
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
COMMENTS:
D-3.2.1 Schedulers interface with
contractors
The Purpose of
Schedulers interface with contractors function
is similar to function
(D-3.2) Work management (planning stage) above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
COMMENTS:
D-3.2.2 Schedulers schedule work
crews for scheduled work
The Purpose of
Schedulers schedule work crews for scheduled work function
is similar to function
(D-3.2) Work management (planning stage) above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
COMMENTS:
D-3.2.3 System operators review and
approve scheduled work
The Purpose of
System operators review and approve scheduled work function
is similar to function
(D-3.2) Work management (planning stage) above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
COMMENTS:
D-3.2.4 Schedulers identify assets
required for scheduled work
The Purpose of
Schedulers identify assets required for scheduled work function
is similar to function
(D-3.2) Work management (planning stage) above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
COMMENTS:
D-3.2.5 Work crews perform
scheduled work, coordinating with operators for switching operations
The Purpose of Work
crews perform scheduled work, coordinating with operators for switching
operations function
is similar to function
(D-3.2) Work management (planning stage) above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
COMMENTS:
D-3.3 Operators prepare (plan) for
storm conditions and other alerting situations based on weather data, other
alarming systems, and history
The Purpose of
Operators prepare (plan) for storm conditions and other alerting situations
based on weather data, other alarming systems, and history
function
is to
Prepare for major event conditions following relevant guidelines
Providing necessary information to relevant parties
Changing schedules
Settings
Work permits
Etc
directly involving
Different utility departments
Field crews
DERs
Major customers
performing
Warnings
Schedule changes
Work recalls
Setting changes
Changes of automated system modes of operation
Changing alarm tolerances
with key interfaces between
DisCos and TransCO
DisCos and ISO/RTO
DisCos and field crews
DisCos and customers
DisCos and DER owners
DisCos and weather systems
DisCos and security institutions
with communication
configuration requirements of
WAN
LAN
Mobile
Internet
One-to-many
with quality of service
requirements of
High availability
Data accuracy
with security requirements of
Prevention of interference
with data management requirements
of
Different types of data over different types of communications
with constraints of
Diversity of non-standard situations
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
3.0 |
3.0 |
2.4 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration = 2 due to diversity of multiple communications
Quality of Service =2 due to accuracy and clarity requirements
Security =2 due to planning for major events including terror alarm conditions
Data Management =3
Due to high volume data model for look-ahead studies
Constraints = 3 due to immature applications ( no optimization and coordination)
D-3.3.1 Change recloser settings
The Purpose of
Change recloser settings function
is similar to function
(D-3.3) Operators prepare (plan) for storm conditions and other alerting
situations based on weather data, other alarming systems, and history above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
3.0 |
3.0 |
2.4 |
COMMENTS:
D-3.3.2 Change alarm thresholds
The Purpose of
Change alarm thresholds function
is similar to function
(D-3.3) Operators prepare (plan) for storm conditions and other alerting
situations based on weather data, other alarming systems, and history above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
3.0 |
3.0 |
2.4 |
COMMENTS:
D-3.3.3 Prepare for transformer
clipping (e.g. Solar wind raising ground DC offset)
The Purpose of
Prepare for transformer clipping (e.g. Solar wind raising ground DC offset)
function
is similar to function
(D-3.3) Operators prepare (plan) for storm conditions and other alerting
situations based on weather data, other alarming systems, and history above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
3.0 |
3.0 |
2.4 |
COMMENTS:
D-4 Real-time operations
The Purpose of
Real-time operations function
is to
Monitor and control the distribution operations in real time providing timely
and reliable information and control by the operators and automated applications
Implement scheduled working orders
Following reliability
Power quality
Safety
And efficiency standards
And provide adequate recording of the activities
directly involving
Field IEDs
Substation automation
Real-time databases
Data links to other real-time systems (EMS
OMS
MO)
Communication systems
Field crews
Other utility departments
TransCos
ISO/RTO
DER's
Major customers
Market participants
performing
Fast data acquisition
Reasonability check
Alarm processing
Crew dispatching
Coordination with TransCOs
ISO/RTO
And market participants
Event recording
Supervisory status and setpoint control
with key interfaces between
SCADA and field IEDs
SCADA and mobile computers
DisCOs and TransCOs
DisCOs and RTO/ISO
DisCOs and DER owners
Distribution Automation System (DAS) and SCADA+G82
DisCos and major customers
DisCos and customer representatives (serving entities)
SCADA and OMS
Real-time databases and work management databases
Operation
Work management
Relay protection
Power quality
IT
And OMS departments of DisCo
DisCos and MOS
DisCos and customers
with communication configuration
requirements of
WAN
LAN
Internet
One-to-many
Mobile
Special media
with quality of service
requirements of
High availability
Response
Data accuracy
Data frequency
with security requirements of
Prevention of interference
with data management requirements
of
Timely access
Large historic databases
with constraints of
Difficult to change legacy field IEDs
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration = 3 due to data gathering from multiple sources via different
communication systems
Quality = 3 due to high availability
Response
Data accuracy
Data frequency
Security = 3 for prevention of interference
Data Management =3 for timely access
Large historic databases
Constraints/concerns = 2 due to difficulty to change legacy field IEDs
D-4.1 SCADA system monitors
distribution system
The Purpose of
SCADA system monitors distribution system function
is to
Monitor and control the distribution operations in real time providing timely
and reliable information and control by the operators and automated applications
Implement scheduled working orders
Following reliability
Power quality
Safety
And efficiency standards
And provide adequate recording of the activities
directly involving
Field IEDs
Substation automation
Real-time databases
Data links to other real-time systems (EMS
OMS
MO)
Communication systems
performing
Fast data acquisition
Reasonability check
Alarm processing
Event recording
Supervisory status and setpoint control
with key interfaces between
SCADA and field IEDs
SCADA and mobile computers
DisCOs and TransCOs
DisCOs and RTO/ISO
DisCOs and DER owners
DisCos and major customers
DisCos and customer representatives (serving entities)
SCADA and OMS
Real-time databases and work management databases
with communication configuration
requirements of
WAN
LAN
Internet
One-to-many
Mobile
Special media
with quality of service
requirements of
High availability
Response
Data accuracy
Data frequency
with security requirements of
Prevention of interference
with data management requirements
of
Timely access
Large historic databases
with constraints of
Difficult to change legacy field IEDs
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration = 3 due to data gathering from multiple sources via different
communication systems
Quality = 3 due to high availability
Response
Data accuracy
Data frequency
Security = 3 for prevention of interference
Data Management =3 for timely access
Large historic databases
Constraints/concerns = 3 due to difficulty to change legacy field IEDs
D-4.1.1 Monitor plant state
(open/close)
The Purpose of
Monitor plant state (open/close) function
is similar to function
(D-4.1) SCADA system monitors distribution system above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-4.1.2 Monitor system activity and
load (current, voltage, frequency, energy)
The Purpose of
Monitor system activity and load (current, voltage, frequency, energy)
function
is similar to function
(D-4.1) SCADA system monitors distribution system above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-4.1.3 Monitor equipment condition
(overheat, overload, battery level, capacity)
The Purpose of
Monitor equipment condition (overheat, overload, battery level, capacity)
function
is similar to function
(D-4.1) SCADA system monitors distribution system above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-4.1.4 Monitor environmental
(fire, smoke, temperature, sump level)
The Purpose of
Monitor environmental (fire, smoke, temperature, sump level)
function
is similar to function
(D-4.1) SCADA system monitors distribution system above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-4.1.5 Monitor security (door
alarm, intrusion, cyber attack, audio/video recording)
The Purpose of
Monitor security (door alarm, intrusion, cyber attack, audio/video recording)
function
is similar to function
(D-4.1) SCADA system monitors distribution system above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-4.2 Operators handle alarms
The Purpose of
Operators handle alarms function
is to
Time notice
React
And acknowledge alarming situation in the power system
directly involving
SCADA
Shift operators
Work management
Relay protection
Power quality department
OMS
DisCo management
Field crews
performing
Intelligent alarm processing
Reporting
Acknowledgement
with key interfaces between
Operation
Work management
Relay protection
Power quality
And OMS departments of DisCo
DisCos and TransCo
DisCos and ISO/RTO
DisCos and DER owners
DisCos and major customers
DisCos and customer representatives (serving entities)
DisCos and field crews
with communication configuration
requirements of
WAN
LAN
Mobile
Internet
One-to-many
with quality of service
requirements of
High availability
Accuracy
Possible high volume (many parameters changing- high activity conditions)
with security requirements of
Authorized access
with data management requirements
of
High speed processing of multiple data
with constraints of
Immature applications for intelligent alarm processing
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration = 3 due to data gathering from multiple sources via different
communication systems
Quality = 3 due to high availability
Fast response
Data accuracy
Security = 3 for prevention of interference
Authorized access
Data Management =3 for timely access
Speed of processing high volumes of data
Constraints/concerns =3 due to immaturity of intelligent alarm processing
D-4.2.1 Intelligent alarm
processing by SCADA system
The Purpose of
Intelligent alarm processing by SCADA system function
is similar to function
(D-4.2) Operators handle alarms above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-4.2.2 Distribution of alarms to
non-operators
The Purpose of
Distribution of alarms to non-operators function
is similar to function
(D-4.2) Operators handle alarms above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-4.3 Operators dispatch field
crews for scheduled work
The Purpose of
Operators dispatch field crews for scheduled work function
is to to timely and safely implement scheduled work
directly involving
Operators
Field crews
performing
Work permits
Work description
Authorization of switching orders
Verification of safety rules and actions
with key interfaces between
DisCos and field crews
DisCos and major customers
with communication configuration
requirements of
LAN
Mobile
Internet
with quality of service
requirements of
Accuracy and clarity of information
with security requirements of
Authorized access
with data management requirements
of
Transmitting drawings and maps over mobile communications
with constraints of
Diverse data nature
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
3.0 |
2.0 |
2.0 |
2.2 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration = 2 due to data gathering and transmitting via multiple and
different communication systems
Quality = 2 due to data accuracy and clarity
Security = 3 for prevention of interference
Authorized access
Data Management =2 due transmitting maps and drawings over mobile
Constraints/concerns =2 diverse structure of data
D-4.3.1 Crew acquires drawings,
previous records, customer profile
The Purpose of Crew
acquires drawings, previous records, customer profile function
is similar to function
(D-4.3) Operators dispatch field crews for scheduled work above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
3.0 |
2.0 |
2.0 |
2.2 |
COMMENTS:
D-4.3.2 Operator establishes limits
on what crew is permitted to do
The Purpose of
Operator establishes limits on what crew is permitted to do
function
is similar to function
(D-4.3) Operators dispatch field crews for scheduled work above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
3.0 |
2.0 |
2.0 |
2.2 |
COMMENTS:
D-4.3.3 Using mobile radio system
The Purpose of Using
mobile radio system function
is similar to function
(D-4.3) Operators dispatch field crews for scheduled work above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
3.0 |
2.0 |
2.0 |
2.2 |
COMMENTS:
D-4.3.4 Using mobile computing
The Purpose of Using
mobile computing function
is similar to function
(D-4.3) Operators dispatch field crews for scheduled work above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
3.0 |
2.0 |
2.0 |
2.2 |
COMMENTS:
D-4.4 Work crews provide
information for updating relevant databases
The Purpose of Work
crews provide information for updating relevant databases
function
is to
To update databases in the course of the work progress and, as soon, as possible
after completion
Before the facility is put in service
directly involving
Field crews
IT personnel
Maintenance management
performing
Recording data using standard forms
Transmitting form via available communications
Populating databases
And verifying consistency of data
with key interfaces between
DIsCo operation
Work management
Maintenance
And IT departments
DisCos and field crews
with communication configuration
requirements of
LAN
Internet
Mobile communications
with quality of service
requirements of
High accuracy and clarity of information
with security requirements of
Limited disclosure
with data management requirements
of
Drawing and maps transmitted over mobile communications
Limited time for verification of transmittal
with constraints of
Legacy performance
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
2.0 |
1.0 |
1.2 |
COMMENTS:
The following comments were collected during the team rating review:
Data Management = 2 due to transmittal of graphic data over mobile
communications
D-4.4.1 Work crews log activities
and results of tests
The Purpose of Work
crews log activities and results of tests function
is similar to function
(D-4.4) Work crews provide information for updating relevant databases
above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
2.0 |
1.0 |
1.2 |
COMMENTS:
D-4.4.2 Work crews identifies
assets installed and/or removed
The Purpose of Work
crews identifies assets installed and/or removed function
is similar to function
(D-4.4) Work crews provide information for updating relevant databases
above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
2.0 |
1.0 |
1.2 |
COMMENTS:
D-4.5 Operators perform supervisory
and/or manual (using field crews) control of switching operations, load tap
changers and voltage controllers, capacitor statuses
The Purpose of
Operators perform supervisory and/or manual (using field crews) control of
switching operations, load tap changers and voltage controllers, capacitor
statuses function
is to
Controlling the distribution operations in real time providing implementation of
scheduled working orders
Load balancing
Power quality
Meeting contractual obligations with TransCos and
DERs
And customers
Following reliability
Power quality
Safety
And efficiency standards
directly involving
Shift operators
Field crews
SCADA
TransCos
Major customers
performing
Monitoring operating conditions
Generating switching orders
Dispatching and managing field crews
with key interfaces between
DisCos and field crews
DisCos and TransCos
DisCos and major customers
SCADA and field IEDs
with communication configuration
requirements of
WAN
LAN
Mobile
SCADA communications
Internet
with quality of service
requirements of
High availability
Data accuracy
Data clarity
High frequency
with security requirements of
Prevention of interference
Authorized access
with data management requirements
of
Timely access
with constraints of
Limited time and ability for optimal decision making in complex situation
Lack of experience of new personnel
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration = 3 due to data gathering from multiple sources via different
communication systems
Quality = 3 due to high availability
Response
Data accuracy
Data frequency
Security = 3 for prevention of interference
Data Management =3 for timely access
Large historic databases
Constraints/concerns = 3 due to difficulty to change legacy field IEDs
D-4.6 Operator defines objectives
and other parameters of DA functions, e.g
The Purpose of
Operator defines objectives and other parameters of DA functions, e.g
function
is to
Use the flexibility of advanced distribution automation applications to adjust
to the changing objectives and needs of DisCos
Customers
TransCos
ISO/RTO
And MOS
directly involving
Distribution Automation Systems
EMS
MOS
OMS
TransCos
ISO/RTO
DER
Customers
performing
Adjustment of option provided by the DA applications
with key interfaces between
DisCos and EMS
DisCos and MOS
Distribution Automation System (DAS) and SCADA
with communication configuration
requirements of
WAN
LAN
with quality of service
requirements of
High availability
Data accuracy
User-friendly interface
with security requirements of
Authorized access
with data management requirements
of
Timely access
with constraints of
User-friendly interface
New applications
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
3.0 |
1.0 |
2.0 |
1.8 |
COMMENTS:
The following comments were collected during the team rating review:
Quality = 2 due to high availability
Response
Data accuracy
User-friendly interface
Security = 3 for prevention of interference
Authorized access
Constraints/concerns = 2 due to new applications
D-4.6.1 Closed-loop control of
service restoration function
The Purpose of
Closed-loop control of service restoration function function
is similar to function
(D-4.6) Operator defines objectives and other parameters of DA functions, e.g
above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
3.0 |
1.0 |
2.0 |
1.8 |
COMMENTS:
D-4.6.2 Use emergency limits for
service restoration
The Purpose of Use
emergency limits for service restoration function
is similar to function
(D-4.6) Operator defines objectives and other parameters of DA functions, e.g
above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
3.0 |
1.0 |
2.0 |
1.8 |
COMMENTS:
D-4.6.3 Provide volt/var support
for transmission
The Purpose of
Provide volt/var support for transmission function
is similar to function
(D-4.6) Operator defines objectives and other parameters of DA functions, e.g
above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
3.0 |
1.0 |
2.0 |
1.8 |
COMMENTS:
D-4.6.4 Provide Peak Load reduction
within voltage quality limits
The Purpose of
Provide Peak Load reduction within voltage quality limits
function
is similar to function
(D-4.6) Operator defines objectives and other parameters of DA functions, e.g
above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
3.0 |
1.0 |
2.0 |
1.8 |
COMMENTS:
D-4.6.5 Provide Peak Load reduction
within voltage emergency limits
The Purpose of
Provide Peak Load reduction within voltage emergency limits
function
is similar to function
(D-4.6) Operator defines objectives and other parameters of DA functions, e.g
above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
3.0 |
1.0 |
2.0 |
1.8 |
COMMENTS:
D-5 Automation of distribution
operations
The Purpose of
Automation of distribution operations function
is to
Automate data preparation
Optimal decision making
And control of distribution operations in a coordinated with other power systems
manner
directly involving
Interfacing with different corporate databases
EMS
OMS
CIS
MOS
Comprehensive near real-time simulations of the operating conditions
Near real-time optimization
And real-time control of distribution operations
performing
Database consistency checking and corrections
Power system model integrity checking
Periodic and by-event system modeling and analysis
Current and predictive alarming
Contingency analysis
Volt/var optimization
Fault location
Isolation
And service restoration
Multi-level feeder reconfiguration
Operation diagnostic
Logging and reporting
Etc
with key interfaces between
Distribution Automation System (DAS) and SCADA
DisCOs/DAS and WMS
DAS and field crews
DAS and field IEDs
DisCOs/DAS and DER owners
DisCOs/DAS and TransCOs/EMS
DisCOs/DAS and RTO/ISO/EMS
DisCOs/DAS and MOS
DisCos/DAS and major customers
DisCos/DAS and customer representatives (serving entities)
DAS and OMS
DAS and AM/FM/GIS/CIS databases
Real-time databases and work management databases
with communication configuration
requirements of
WAN
LAN
Internet
One-to-many
Mobile
Special media
with quality of service
requirements of
High availability
Response
Data accuracy
Data frequency
High volume of databases
And high speed of processing high volume data
with security requirements of
High security
with data management requirements
of
Management of many large databases in a synchronized manner with strict time
constraints
with constraints of
Legacy paradigm of the utility personnel
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration = 3 due to data gathering from multiple sources via different
communication systems, interfaces with other real-time databases, integration
into transmission and market
Quality = 3 due to high availability, response, data accuracy, data frequency
Security = 3 for prevention of
interference Data Management =3 for timely access, coordination of different
databases, time updates without interruption of operations, Constraints/concerns
= 3 due to difficulty to change legacy paradigm of the utility personnel, high
performance requirements for the applications
D-5.1 DA system updates power
system model and analyzes distribution operations
The Purpose of DA
system updates power system model and analyzes distribution operations
function
is to
Running in real-time unbalanced distribution power flow for the dynamically
changing distribution operating conditions
Analyze the results
And provide the operator with the summary results of the analysis and the DA
applications with pseudo-measurements for each element of the distribution
system down to the load centers in the secondaries
directly involving
SCADA
AF/FM
CIS
DA real-time power database
And other corporate databases
performing
Load modeling
Topology modeling
State estimation
Facility modeling
Power calculations and analyses of its results
And reporting
with key interfaces between
DAS and SCADA
DisCOs/DAS and TransCOs/EMS
DisCOs/DAS and RTO/ISO/EMS
DAS and OMS
DAS and AM/FM/GIS/CIS databases
DisCOs/DAS and MOS
DisCos/DAS and major customers
DisCos/DAS and customer representatives (serving entities)
with communication configuration
requirements of
WAN
LAN
SCADA communications
with quality of service
requirements of
High availability
Response
Data accuracy
Data volume
Data frequency (every 5 minutes)
User-friendly interface
with security requirements of
Authorized access
with data management requirements
of
Large databases
Comprehensive modeling
with constraints of
New application
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration = 3 due to data gathering from multiple sources via different
communication systems, interfaces with other and different databases
Quality = 3 due to high availability, response, data accuracy, data frequency
Security = 3 for prevention of interference
Data Management =3 for timely access, coordination of different databases of
large volumes, time updates without interruption of operations
Constraints/concerns = 3 due to difficulty to change legacy paradigm of the
utility personnel, high performance requirements for the applications
D-5.1.1 Update topology model
The Purpose of
Update topology model function
is similar to function
(D-5.1) DA system updates power system model and analyzes distribution
operations above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-5.1.2 Update facilities model
The Purpose of
Update facilities model function
is similar to function
(D-5.1) DA system updates power system model and analyzes distribution
operations above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-5.1.3 Update load model
The Purpose of
Update load model function
is similar to function
(D-5.1) DA system updates power system model and analyzes distribution
operations above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-5.1.4 Update relevant
transmission model
The Purpose of
Update relevant transmission model function
is similar to function
(D-5.1) DA system updates power system model and analyzes distribution
operations above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-5.1.5 Update and analyze
real-time operating conditions using distribution power flow/state estimation
The Purpose of
Update and analyze real-time operating conditions using distribution power
flow/state estimation function
is similar to function
(D-5.1) DA system updates power system model and analyzes distribution
operations above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-5.1.6 Update system capacity
based on real-time equipment monitoring data
The Purpose of
Update system capacity based on real-time equipment monitoring data
function
is similar to function
(D-5.1) DA system updates power system model and analyzes distribution
operations above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-5.1.7 Issue alarming/warning
messages to the operator
The Purpose of Issue
alarming/warning messages to the operator function
is similar to function
(D-5.1) DA system updates power system model and analyzes distribution
operations above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-5.1.8 Generate distribution
operation reports and logs
The Purpose of
Generate distribution operation reports and logs function
is similar to function
(D-5.1) DA system updates power system model and analyzes distribution
operations above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-5.2 DA system performs fault
location, fault isolation, and service restoration
The Purpose of DA
system performs fault location, fault isolation, and service restoration
function
is to
Automatically define
Isolate the faulted section(s)) of the distribution system and maximally and
optimally restore service to the customers utilizing all available distribution
facilities for the backup of de-energized customers without unacceptable
violations of the operating parameters
directly involving
SCADA
AF/FM
CIS
OMS
DA real-time power database
And other corporate databases
performing
Fault data analysis
Status changes analysis
Comprehensive search of alternative supply for the de-energized portion of
distribution system
Switching order generation
Recommendation and/or execution
with key interfaces between
DAS and SCADA
DisCOs/DAS and TransCOs/EMS
DisCOs/DAS and RTO/ISO/EMS
DAS and OMS
DAS and AM/FM/GIS/CIS databases
with communication configuration
requirements of
WAN
LAN
SCADA communications
with quality of service
requirements of
High availability
Response
Data accuracy
Data volume
Data frequency (every 5 minutes)
User-friendly interface
with security requirements of
Authorized Access
Prevention of interference
with data management requirements
of
Management of high volume database and numerous alternative solutions within
seconds
with constraints of
New application
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration = 3 due to data gathering from multiple sources via different
communication systems, interfaces with other real-time databases
Quality = 3 due to high availability, response, data accuracy, data frequency,
user-friendly interface
Security = 3 for prevention of interference
Data Management =3 for management of high volume database and numerous
alternative solutions within seconds
Constraints/concerns = 3 due to difficulty to change legacy paradigm of the
utility personnel, high performance requirements for the application
D-5.2.1 DA indicates the faults
cleared by controllable protective devices
The Purpose of
DA indicates the faults cleared by controllable protective devices
function
is similar to function
(D-5.2) DA system performs fault location, fault isolation, and service
restoration above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-5.2.1.1 Distinguish faults
cleared by fuses
The Purpose of
Distinguish faults cleared by fuses function
is similar to function
(D-5.2.1) DA indicates the faults cleared by controllable protective devices
above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-5.2.1.2 Distinguish momentary
outages
The Purpose of
Distinguish momentary outages function
is similar to function
(D-5.2.1) DA indicates the faults cleared by controllable protective devices
above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-5.2.1.3 Distinguish inrush/cold
load current
The Purpose of
Distinguish inrush/cold load current function
is similar to function
(D-5.2.1) DA indicates the faults cleared by controllable protective devices
above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-5.2.2 DA determines the faulted
sections based on SCADA fault indications and protection lockout signals
The Purpose of DA
determines the faulted sections based on SCADA fault indications and protection
lockout signals function
is similar to function
(D-5.2) DA system performs fault location, fault isolation, and service
restoration above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-5.2.3 DA estimates the probable
fault locations based on SCADA fault current measurements and real-time fault
analysis
The Purpose of DA
estimates the probable fault locations based on SCADA fault current measurements
and real-time fault analysis function
is similar to function
(D-5.2) DA system performs fault location, fault isolation, and service
restoration above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-5.2.4 DA determines the
fault-clearing non-monitored protective device based on trouble call inputs and
dynamic connectivity model
The Purpose of DA
determines the fault-clearing non-monitored protective device based on trouble
call inputs and dynamic connectivity model function
is similar to function
(D-5.2) DA system performs fault location, fault isolation, and service
restoration above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-5.2.5 DA generates switching
orders for fault isolation, service restoration, and return to normal (taking
into account the availability of remotely controlled switching devices, feeder
paralleling, and cold-load pickup)
The Purpose of DA
generates switching orders for fault isolation, service restoration, and return
to normal (taking into account the availability of remotely controlled switching
devices, feeder paralleling, and cold-load pickup) function
is similar to function
(D-5.2) DA system performs fault location, fault isolation, and service
restoration above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-5.2.5.1 Operators executes
switching orders by using SCADA
The Purpose of
Operators executes switching orders by using SCADA function
is similar to function
(D-5.2.5) DA generates switching orders for fault isolation, service
restoration, and return to normal (taking into account the availability of
remotely controlled switching devices, feeder paralleling, and cold-load pickup)
above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-5.2.5.2 Operator authorizes the
DA application to execute the switching orders in closed-loop mode
The Purpose of
Operator authorizes the DA application to execute the switching orders in
closed-loop mode function
is similar to function
(D-5.2.5) DA generates switching orders for fault isolation, service
restoration, and return to normal (taking into account the availability of
remotely controlled switching devices, feeder paralleling, and cold-load pickup)
above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-5.2.6 DA system isolates the
fault and restores service automatically by-passing the operator based on
operator’s authorization in advance
The Purpose of DA
system isolates the fault and restores service automatically by-passing the
operator based on operator’s authorization in advance function
is similar to function
(D-5.2) DA system performs fault location, fault isolation, and service
restoration above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-5.2.7 DA considers creation of
islands supported by distributed resources for service restoration
The Purpose of DA
considers creation of islands supported by distributed resources for service
restoration function
is similar to function
(D-5.2) DA system performs fault location, fault isolation, and service
restoration above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-5.3 DA system performs
multi-level feeder reconfiguration for different objectives
The Purpose of DA
system performs multi-level feeder reconfiguration for different objectives
function
is to
Maximally and optimally utilize all available distribution facilities for load
balancing
Voltage equalization
Reliability maximization
Loss minimization transmission unloading under normal
Maintenance
And emergency conditions
Without unacceptable violations of the operating parameters
directly involving
SCADA
AF/FM
CIS
OMS
WMS
DA real-time power database
And other corporate databases
Field crews
DERs
performing
Status changes analysis
Comprehensive search of alternative supply connectivity
Switching order generation
Recommendation and/or execution
with key interfaces between
DAS and SCADA
DisCOs/DAS and TransCOs/EMS
DisCOs/DAS and RTO/ISO/EMS
DAS and OMS
DAS and AM/FM/GIS/CIS databases
DisCos/DAS and WMS
DisCos/DAS and field crews
DisCos/DAS and major customers
Real-time databases and work management databases
with communication configuration
requirements of
WAN
LAN
SCADA communications
Internet
Mobile
with quality of service
requirements of
High availability
Response
Data accuracy
Data volume
User-friendly interface
with security requirements of
Authorized Access
Prevention of interference
with data management requirements
of
Management of high volume database and numerous alternative solutions
with constraints of
New application
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration =2due to data gathering from multiple sources via different
communication systems, interfaces with other real-time databases
Quality = 2 due to high availability, response, data accuracy, user-friendly
interface
Security = 2 for prevention of interference
Data Management =2 for management of high volume database and numerous
alternative solutions
Constraints/concerns = 2 due to difficulty to change legacy paradigm of the
utility personnel, high performance requirements for the application
D-5.3.1 Service restoration
The Purpose of
Service restoration function
is similar to function
(D-5.3) DA system performs multi-level feeder reconfiguration for different
objectives above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
COMMENTS:
D-5.3.2 Overload elimination
The Purpose of
Overload elimination function
is similar to function
(D-5.3) DA system performs multi-level feeder reconfiguration for different
objectives above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
COMMENTS:
D-5.3.3 Load balancing
The Purpose of Load
balancing function
is similar to function
(D-5.3) DA system performs multi-level feeder reconfiguration for different
objectives above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
COMMENTS:
D-5.3.4 Transmission facilities
overload
The Purpose of
Transmission facilities overload function
is similar to function
(D-5.3) DA system performs multi-level feeder reconfiguration for different
objectives above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
COMMENTS:
D-5.3.5 Loss minimization
The Purpose of Loss
minimization function
is similar to function
(D-5.3) DA system performs multi-level feeder reconfiguration for different
objectives above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
COMMENTS:
D-5.3.6 Voltage balancing
The Purpose of
Voltage balancing function
is similar to function
(D-5.3) DA system performs multi-level feeder reconfiguration for different
objectives above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
COMMENTS:
D-5.3.7 Reliability improvement
The Purpose of
Reliability improvement function
is similar to function
(D-5.3) DA system performs multi-level feeder reconfiguration for different
objectives above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
COMMENTS:
D-5.4 DA performs relay protection
re-coordination
The Purpose of DA
performs relay protection re-coordination function
is to adjust relay protection settings to the real-time
conditions based on preset rules
directly involving
Real-time connectivity models
SCADA
DERs
performing
Relay protection settings and switch mode operation analyses for real-time
connectivity tagging and weather conditions
with key interfaces between
DAS and SCADA
DisCos/DAS and field IEDs
DisCo and DER
with communication configuration
requirements of
LAN
SCADA
with quality of service
requirements of
High availability
Response
Data accuracy
User-friendly interface
with security requirements of
Authorized Access
Prevention of interference
with data management requirements
of
Management of high volume data for seeking optimal solutions
with constraints of
New application
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration =2 due to data gathering from multiple sources via different
communication systems, interfaces with other real-time databases
Quality = 2 due to high availability, response, data accuracy, user-friendly
interface
Security = 2 for prevention of interference
Data Management =2 for management of high volume data for optimization
Constraints/concerns = 2 due to difficulty to change legacy paradigm of the
utility personnel
D-5.4.1 After feeder
reconfiguration
The Purpose of After
feeder reconfiguration function
is similar to function
(D-5.4) DA performs relay protection re-coordination above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
COMMENTS:
D-5.4.2 In case of changed
conditions for fuse saving
The Purpose of In
case of changed conditions for fuse saving function
is similar to function
(D-5.4) DA performs relay protection re-coordination above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
COMMENTS:
D-5.5 DA system optimally controls
volt/var by changing the states of voltage controllers, shunts, and distributed
resources in a coordinated manner for different objectives under normal and
emergency conditions
The Purpose of DA
system optimally controls volt/var by changing the states of voltage
controllers, shunts, and distributed resources in a coordinated manner for
different objectives under normal and emergency conditions
function
is to
Power quality improvement
Non-intrusive load management
Load balancing
Transmission operation support
directly involving
SCADA
AF/FM
CIS
DA real-time power database
And other corporate databases
Voltage and capacitor controller
DERs
performing
Simulation and optimization calculations
Implementation of optimal settings and statuses of controllable devices in
coordinated manner in closed-loop mode of operations
with key interfaces between
DAS and SCADA
DAS and DER owners
DisCos/DAS and field IEDs
DisCOs/DAS and TransCOs/EMS
DisCOs/DAS and RTO/ISO/EMS
DisCOs/DAS and MOS
DisCos/DAS and major customers
DisCos/DAS and customer representatives (serving entities)
with communication configuration
requirements of
WAN
LAN
SCADA
with quality of service
requirements of
High availability
Response
Data accuracy
Data volume
High frequency
User-friendly interface
with security requirements of
Authorized Access
Prevention of interference
with data management requirements
of
Management of high volume database and numerous alternative solutions
with constraints of
New application with high performance requirements
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration = 3 due to data gathering from multiple sources via different
communication systems, interfaces with other real-time databases
Quality = 3 due to high availability, response, data accuracy, data frequency,
user-friendly interface
Security = 3 for prevention of interference
Data Management =3 for management of high volume database and numerous
alternative solutions within seconds
Constraints/concerns = 3 due to difficulty to change legacy paradigm of the
utility personnel, high performance requirements for the application
D-5.5.1 Power quality improvement
The Purpose of Power
quality improvement function
is similar to function
(D-5.5) DA system optimally controls volt/var by changing the states of voltage
controllers, shunts, and distributed resources in a coordinated manner for
different objectives under normal and emergency conditions above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-5.5.2 Overload
elimination/reduction
The Purpose of
Overload elimination/reduction function
is similar to function
(D-5.5) DA system optimally controls volt/var by changing the states of voltage
controllers, shunts, and distributed resources in a coordinated manner for
different objectives under normal and emergency conditions above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-5.5.3 Load management
The Purpose of Load
management function
is similar to function
(D-5.5) DA system optimally controls volt/var by changing the states of voltage
controllers, shunts, and distributed resources in a coordinated manner for
different objectives under normal and emergency conditions above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-5.5.4 Transmission operation
support in accordance with T&D contracts
The Purpose of
Transmission operation support in accordance with T&D contracts
function
is similar to function
(D-5.5) DA system optimally controls volt/var by changing the states of voltage
controllers, shunts, and distributed resources in a coordinated manner for
different objectives under normal and emergency conditions above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-5.5.5 Loss minimization in
distribution and transmission
The Purpose of Loss
minimization in distribution and transmission function
is similar to function
(D-5.5) DA system optimally controls volt/var by changing the states of voltage
controllers, shunts, and distributed resources in a coordinated manner for
different objectives under normal and emergency conditions above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-6 Real-time emergency operations
The Purpose of
Real-time emergency operations function
is to provide maximally possible self-healing properties
of distribution systems including disaster conditions
directly involving
Emergency automatic schemes and devices
More reliable distribution system structures
Distributed resources
Distribution automation
Fast and high capacity communications
performing
Fast (automatic) location and isolation of faults
Backup of services
And automatic or automated service restoration
with key interfaces between
Substation and feeder relay protection schemes and SCADA/DAS
SCADA/DAS and DER owners
Operators and SCADA
Operators and DER owners
Operators and TransCo
Operators and DAS
Operators and DIsCo operation
Work management
Maintenance
And IT departments
Operators and field crews
Operators and customers
Operators and OMS
Operators and Maintenance department
DisCo and customers
OMS and Customer Information System
OMS and SCADA
OMS and AMR system
OMS and call in fault detection system
DAS and OMS
OMS and WMS
OMS and field crews
DisCo and affected customers
DisCo and external warning systems
DAS and SCADA
DisCOs/DAS and TransCOs/EMS
DisCOs/DAS and RTO/ISO/EMS
DisCOs/DAS and MOS
DisCos/DAS and DER owners
DisCos/DAS and major customers
DisCos/DAS and customer representatives (serving entities)
DAS and AM/FM/GIS/CIS databases
SCADA and field IEDs
with communication configuration
requirements of
WAN
LAN
Internet
One-to-many
SCADA communications
Mobile
High speed
High capacity
Two-way special media
with quality of service
requirements of
High availability
Extremely fast response
Data accuracy
High data frequency
High volume of databases
And high speed of processing high volume data
with security requirements of
High security
with data management requirements
of
Management of many large databases and high intensity of real-time data in a
synchronized manner with strict time constraints
with constraints of
Legacy paradigm of the utility personnel
Safety requirements
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration = 3 due to data gathering from multiple sources via different
communication systems, interfaces with other real-time databases, integration
into transmission
Quality = 3 due to high availability, response, data accuracy, data frequency
Security =3 for prevention of
interference due to safety concerns, data
Data Management =3 for timely access, coordination of different databases, time
updates without interruption of operations,
Constraints/concerns = 3 due to
difficulty to change legacy paradigm of the utility personnel, high performance
requirements for the applications and due to the fact that a self-healing
distribution system under disastrous conditions is the most challenging function
in the power system operations
The comments indicate a similar interface (and rating) to a
non-existent or mis-labeled function. -- Peter Sanza -
05 Apr 2003
D-6.1 Protection equipment performs
system protection actions
The Purpose of
Protection equipment performs system protection actions function
is to fast detection of disturbances and automatic actions
minimizing the damage
directly involving
Relay protection schemes
Automatic load shedding systems
DER separation schemes
Pre-arming applications
performing
Fast disconnection of faulted facilities
Automatic load balancing based on local voltage and frequency measurements
And other fast acting automatic actions based on local measurements and on
locally or remotely installed settings and adjustment of the setup of the
automatic schemes by DA applications
with key interfaces between
Substation and feeder relay protection schemes and SCADA/DAS/EMS
SCADA/DAS/EMS and DER owners
with communication configuration
requirements of
SCADA communications
with quality of service
requirements of
Availability
Response
Accuracy
Frequency
with security requirements of
Prevention of interference
Authorized access
with data management requirements
of
Timely access
with constraints of
New applications for pre-arming and intelligence of the local devices
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration = 3 due to data gathering from multiple sources via different
communication systems, interfaces with other real-time databases, integration
into transmission
Quality = 3 due to high availability, response, data accuracy, data frequency
Security =3 for prevention of
interference due to safety concerns, data
Data Management =3 for timely access, coordination of different databases, time
updates without interruption of operations,
Constraints/concerns = 3 due to
difficulty to change legacy paradigm of the utility personnel, high performance
requirements for the applications and due to the fact that a self-healing
distribution system under disastrous conditions is the most challenging function
in the power system operations
D-6.1.1 Fault detection, clearing,
and reclosing
The Purpose of Fault
detection, clearing, and reclosing function
is similar to function
(D-6.1) Protection equipment performs system protection actions above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-6.1.2 Under-frequency
load-shedding
The Purpose of
Under-frequency load-shedding function
is similar to function
(D-6.1) Protection equipment performs system protection actions above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-6.1.3 Under-voltage load-shedding
The Purpose of
Under-voltage load-shedding function
is similar to function
(D-6.1) Protection equipment performs system protection actions above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
D-6.2 Operators manage multiple
emergency alarms
The Purpose of
Operators manage multiple emergency alarms function
is to
Timely detect the disturbance
Prioritize the events
directly involving
SCADA
DA applications
performing
Intelligent alarm processing
Reporting
Acknowledgement
with key interfaces between
Operators and SCADA
Operators and field IEDs
Operators and DER owners
Operators and TransCo
Operators and DAS
with communication configuration
requirements of
SCADA communications
WAN
with quality of service
requirements of
Availability
Response
Accuracy
Frequency
with security requirements of
Prevention of interference
Authorized access
with data management requirements
of
Timely access
with constraints of
New applications for intelligent and fast alarm processing
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration = 2 due to data gathering from multiple sources via different
communication systems
Quality = 2 due to high availability
Response
Data accuracy
Data frequency
Security =2 for prevention of interference
Data Management =2 for timely access
Constraints/concerns = 2 due high performance requirements for the applications
D-6.2.1 Intelligent alarm
processing by SCADA system
The Purpose of
Intelligent alarm processing by SCADA system function
is similar to function
(D-6.2) Operators manage multiple emergency alarms above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
COMMENTS:
D-6.3 SCADA system performs
disturbance monitoring
The Purpose of SCADA
system performs disturbance monitoring function
is to
Recording and analysis of the performance of distribution system and its
components during contingencies
Providing reliable and accurate data storage and analysis
directly involving
SCADA
DA applications
performing
Event recording
Disturbance analysis
with key interfaces between
SCADA and field IEDs
DAS and SCADA
with communication configuration
requirements of
SCADA communications
with quality of service
requirements of
Response
Accuracy
with security requirements of
Prevention of interference
Authorized access
with data management requirements
of
Timely access
with constraints of
New applications
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration = 2 due to data gathering from multiple IEDs within short time
frame
Quality = 2 due to high availability
Response
Data accuracy
Security =2 for prevention of interference
Data Management =2 for timely access
Constraints/concerns = 2 due high performance requirements for the applications
D-6.3.1 Fault current recording
The Purpose of
Fault current recording function
is similar to function
(D-6.3) SCADA system performs disturbance monitoring above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
COMMENTS:
D-6.3.2 Fault location
The Purpose of Fault
location function
is similar to function
(D-6.3) SCADA system performs disturbance monitoring above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
COMMENTS:
D-6.3.3 Event recording
The Purpose of Event
recording function
is similar to function
(D-6.3) SCADA system performs disturbance monitoring above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
COMMENTS:
D-6.4 Operators dispatch field
crews to troubleshoot system and customer power problems
The Purpose of
Operators dispatch field crews to troubleshoot system and customer power
problems function
is to rapidly restore normal operating conditions
directly involving
DisCo operators
Field crews
Customers
performing
Issuing working orders
Working permits
Monitoring progress of work
with key interfaces between
Operators and DIsCo operation
Work management
Maintenance
And IT departments
Operators and field crews
Operators and customers
with communication configuration
requirements of
SCADA
Mobile communications
Internet
with quality of service
requirements of
Data accuracy
Data frequency during the major event
with security requirements of
Authentication
Prevention of interference
with data management requirements
of
Timely access
with constraints of
Mobile computing
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration = 2 due to data transferring over multiple links within short time
frame
Quality = 2 due to high availability
Response
Data accuracy
Security =2 for prevention of interference
Data Management =2 for timely access
Constraints/concerns = 2 due high performance requirements for the mobile
computing applications
D-6.4.1 Mobile radio system
The Purpose of
Mobile radio system function
is similar to function
(D-6.4) Operators dispatch field crews to troubleshoot system and customer power
problems above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
COMMENTS:
D-6.4.2 Mobile computing
The Purpose of
Mobile computing function
is similar to function
(D-6.4) Operators dispatch field crews to troubleshoot system and customer power
problems above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
2.0 |
COMMENTS:
D-6.5 Operators perform emergency
switching operations
The Purpose of
Operators perform emergency switching operations function
is to rapidly restore normal operating conditions
directly involving
SCADA
DA applications
Field crews information
DER information
Major customers' information
performing
Analysis of emergency situation
Creation of switching orders providing safety under rapidly changing operating
conditions
with key interfaces between
Operators and DIsCo operation
Work management
Maintenance
And IT departments
Operators and SCADA
Operators and OMS
Operators and field crews
Operators and customers
with communication configuration
requirements of
LAN
Mobile
Internet
with quality of service
requirements of
Availability
Response
Accuracy
Frequency during major events
with security requirements of
Prevention of interference
Authorized access
with data management requirements
of
Timely access to real-time and OMS databases
with constraints of
New applications
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration = 3 due to data gathering from multiple sources via different
communication systems
Interfaces with other real-time databases
Quality = 3 due to high availability
Response
Data accuracy
Data frequency during limited time-frame
Security =3 for prevention of interference due to safety concerns
Data integrity
Data Management =3 for timely access
Coordination of different databases
Timely updates without interruption of operations
Constraints/concerns = 3 due to high performance requirements for the
applications and due to the fact, that a self-healing distribution system under
disastrous conditions is the most challenging function in the power system
operations
D-6.6 Operators performs intrusive
load management activities
The Purpose of
Operators performs intrusive load management activities function
is to balance load with available supply under severe emergency
conditions
directly involving
DisCo operators
Customers
DA applications
performing
Direct load control
Load curtailment
Load interruption
Load shedding
Emergency volt/var control
with key interfaces between
Operators and customer
Operators and field crews
Operators and SCADA
Operators and DAS
with communication configuration
requirements of
LAN
One-to-many
Mobile
SCADA
with quality of service
requirements of
Availability
with security requirements of
Limited disclosure
with data management requirements
of
Timely access
with constraints of
New applications
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
1.0 |
1.0 |
1.0 |
2.0 |
1.4 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration = 2 due to data transferring over multiple links within short time
frame
Constraints/concerns = 2 due high performance requirements for the applications
D-6.6.1 Operators or planners
identify critical loads (hospitals, etc.) ahead of time
The Purpose of
Operators or planners identify critical loads (hospitals, etc.) ahead of time
function
is similar to function
(D-6.6) Operators performs intrusive load management activities above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
1.0 |
1.0 |
1.0 |
2.0 |
1.4 |
COMMENTS:
D-6.6.2 DA system locks out load
shedding of critical loads
The Purpose of DA
system locks out load shedding of critical loads function
is similar to function
(D-6.6) Operators performs intrusive load management activities above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
1.0 |
1.0 |
1.0 |
2.0 |
1.4 |
COMMENTS:
D-6.6.3 Operator activates direct
load control
The Purpose of
Operator activates direct load control function
is similar to function
(D-6.6) Operators performs intrusive load management activities above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
1.0 |
1.0 |
1.0 |
2.0 |
1.4 |
COMMENTS:
D-6.6.4 Operator activates load
curtailment
The Purpose of
Operator activates load curtailment function
is similar to function
(D-6.6) Operators performs intrusive load management activities above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
1.0 |
1.0 |
1.0 |
2.0 |
1.4 |
COMMENTS:
D-6.6.5 Operator applies load
interruption
The Purpose of
Operator applies load interruption function
is similar to function
(D-6.6) Operators performs intrusive load management activities above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
1.0 |
1.0 |
1.0 |
2.0 |
1.4 |
COMMENTS:
D-6.6.6 Operators enables emergency
load reduction via volt/var control
The Purpose of
Operators enables emergency load reduction via volt/var control
function
is similar to function
(D-6.6) Operators performs intrusive load management activities above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
1.0 |
1.0 |
1.0 |
2.0 |
1.4 |
COMMENTS:
D-6.6.7 Operator applies manual
rolling blackouts
The Purpose of
Operator applies manual rolling blackouts function
is similar to function
(D-6.6) Operators performs intrusive load management activities above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
1.0 |
1.0 |
1.0 |
2.0 |
1.4 |
COMMENTS:
D-6.7 Operator enables emergency
(major event) mode of operations of operation and maintenance personnel, and
enables major event emergency mode of operation of DA applications
The Purpose of
Operator enables emergency (major event) mode of operations of operation and
maintenance personnel, and enables major event emergency mode of operation of DA
applications function
is to prepare the personnel and automated system for
actions under severe emergency conditions
directly involving
DisCo operation and maintenance personnel
DA applications
performing
Announcements of expected conditions
Guidelines to be used
Changes of the setup of DA applications
with key interfaces between
Operators and field crews
Operators and maintenance department
Operators and DAS
with communication configuration
requirements of
LAN
One-to-many
Mobile
SCADA
with quality of service
requirements of
Availability
with security requirements of
Limited disclosure
with data management requirements
of
Low volume
with constraints of
New applications
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
1.0 |
1.0 |
1.0 |
2.0 |
1.4 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration = 2 due to data transferring over multiple links within short time
frame
Constraints/concerns = 2 due high performance requirements for the applications
D-6.8 Outage management systems
collect trouble calls, generate outage information, arrange work for trouble
shooting
The Purpose of
Outage management systems collect trouble calls, generate outage information,
arrange work for trouble shooting function
is to expedite fault location based on customer call in
information by using dynamic connectivity models
directly involving
Troublecall personnel
OMS
Operation personnel
SCADA
performing
Tracing deeenrgized customer locations to the closest common protective device
based on real-time connectivity model supported by SCADA and DMS
Work management
Crew dispatching
with key interfaces between
DisCo and customers
OMS and Customer Information System
OMS and SCADA
OMS and AMR system
OMS and call in fault detection system
DAS and OMS
OMS and WMS
OMS and field crews
with communication configuration
requirements of
LAN
Internet
Telephone systems
Mobile communications
with quality of service
requirements of
High availability
Response
Data frequency
Data volumes
with security requirements of
Authentication
Prevention of interference
with data management requirements
of
Large databases for dynamic support of the connectivity model
Timely access
with constraints of
New applications for integration of information from different sources: SCADA
Customers via telephone
Internet
Call in systems
DA applications
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
2.0 |
2.0 |
3.0 |
2.0 |
2.4 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration = 3 due to data gathering from multiple sources via different
communication systems
Interfaces with other real-time databases
Quality = 2 due to high availability
Response
Data frequency during limited time-frame
Security =2 for prevention of interference due to safety concerns
Data Management =3 for timely access
Coordination of different databases
High volume
Timely updates without interruption of operations
Constraints/concerns = 2 due to high performance requirements for the
applications
D-6.9 Interactive utility-customer
systems inform the customers about the progress of events
The Purpose of
Interactive utility-customer systems inform the customers about the progress
of events function
is to timely updating the customers about the progress of their
service restoration
directly involving
Interactive communication systems between DisCO and customers
performing
Automated messaging based on service restoration progress and association of the
customers' communication nodes with the faulted area
with key interfaces between
DisCo and affected customers
with communication configuration
requirements of
Telephone systems
Internet
with quality of service
requirements of
Availability
Response
Data volume
Data frequency (several times per hour)
with security requirements of
Authentication
Access
with data management requirements
of
Large databases for dynamic support of the association model
Timely access
with constraints of
New application
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
2.0 |
2.0 |
2.0 |
2.0 |
2.2 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration = 3 due to data gathering from multiple sources and data
transmittals via different communication systems
Quality = 2 due to high availability
Response
Data frequency during limited time-frame
Security =2 authentication
Data Management =2 for timely access
High volume
Timely updates
Constraints/concerns = 2 due to new applications
The rating for Configuration does not match the comment. --
Peter Sanza - 05 Apr
2003
D-6.10 DA performs in major event
emergency mode
The Purpose of DA
performs in major event emergency mode function
is to
Automate data preparation
Optimal decision making
And control of distribution operations in a coordinated with other power systems
manner under conditions of major events with more challenging safety and timing
requirements
directly involving
High speed communication systems
Local and centralized automatic/automated systems
DAS applications
performing
Pre-arming of the automatic/automated systems for the operations under major
event conditions and fast acting fault location
Isolation
Service restoration
Feeder reconfiguration
Volt and var control
And operation analysis
with key interfaces between
DisCo and external warning systems
DAS and SCADA
DisCOs/DAS and TransCOs/EMS
DisCOs/DAS and RTO/ISO/EMS
DisCOs/DAS and MOS
DisCOs/DAS and DER owners
DisCos/DAS and major customers
DisCos/DAS and customer representatives (serving entities)
DAS and OMS
DAS and AM/FM/GIS/CIS databases
Real-time databases and work management databases
with communication configuration
requirements of
WAN
LAN
Internet
One-to-many
SCADA communications
Mobile
High speed
High capacity
Two-way special media
with quality of service
requirements of
High availability
Extremely fast response
Data accuracy
High data frequency
High volume of databases
And high speed of processing high volume data
with security requirements of
High security
with data management requirements
of
Management of many large databases and high intensity of real-time data in a
synchronized manner with strict time constraints
with constraints of
Legacy paradigm of the utility personnel
Safety requirements
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
3.0 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration = 3 due to data gathering from multiple sources via different
communication systems, interfaces with other real-time databases, integration
into transmission
Quality = 3 due to high availability, response, data accuracy, data frequency
Security =3 for prevention of
interference due to safety concerns, data
Data Management =3 for timely access, coordination of different databases, time
updates without interruption of operations,
Constraints/concerns = 3 due to
difficulty to change legacy paradigm of the utility personnel, high performance
requirements for the applications and due to the fact that a self-healing
distribution system under disastrous conditions is the most challenging function
in the power system operations
D-7 Post operations
The Purpose of Post
operations function
is to recording and analysis of the performance of distribution
system and its components providing reliable and accurate data storage and
comprehensive analysis
directly involving
All automated systems
Historic databases
Archives
performing
Logging
Archiving
Preparing application performance report
And their analysis
Diagnostic analysis of equipment
with key interfaces between
DAS and SCADA
DAS and other corporate databases
SCADA and historic databases
DAS and historic databases
OMS and historic databases
WMS and historic databases
Historic databases and maintenance personnel
Historic databases and contractors
with communication configuration
requirements of
WAN
LAN
with quality of service
requirements of
Transferring high volume data between various databases
with security requirements of
Moderate security
with data management requirements
of
Easy and timely access to stored data
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
2.0 |
2.0 |
1.4 |
COMMENTS:
The following comments were collected during the team rating review:
Data management = 2 due to volume and high accessibility and retrieval by
different departments
Constraints/Concerns =2 due to the new applications for diagnostic analyses
D-7.1 All systems create and
archive logs and reports
The Purpose of All
systems create and archive logs and reports function
is similar to function
(D-7) Post operations above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
2.0 |
2.0 |
1.4 |
COMMENTS:
D-7.2 System records voice logs of
interaction between operators and field crews
The Purpose of
System records voice logs of interaction between operators and field crews
function
is similar to function
(D-7) Post operations above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
2.0 |
2.0 |
1.4 |
COMMENTS:
D-7.3 All systems transmit reports
to key parties
The Purpose of All
systems transmit reports to key parties function
is similar to function
(D-7) Post operations above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
2.0 |
2.0 |
1.4 |
COMMENTS:
D-7.4 Maintenance personnel of the
automated systems (DAS, OMS, WMS) performs diagnostic analysis of system
performance
The Purpose of
Maintenance personnel of the automated systems (DAS, OMS, WMS) performs
diagnostic analysis of system performance function
is to
Timely determine system performance problems and fix them
Learn about additional functional requirements for the systems
directly involving
System maintenance personnel
Maintenance contractors
System performance reports
performing
Regular and by-event report analyses
Generation of statistics
Evaluation of the system performance
Recommendations for improvement
with key interfaces between
SCADA and historic databases
DAS and historic databases
OMS and historic databases
WMS and historic databases
Historic databases and maintenance personnel
Historic databases and contractors
with communication configuration
requirements of
WAN
LAN
Internet
Other remote-access communication systems
with quality of service
requirements of
Data volumes
Frequency several times per day
with security requirements of
Authentication
Authorized access
with data management requirements
of
Large logs and reports
with constraints of
Easy search of relevant data
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
COMMENTS:
D-7.5 Diagnostic analysis based on
real-time equipment monitoring data, e.g. using predictive models to determine
when the equipment needs maintenance
The Purpose of
Diagnostic analysis based on real-time equipment monitoring data, e.g. using
predictive models to determine when the equipment needs maintenance
function
is to perform diagnostic-based maintenance instead of
time-based in order to enhance the reliability of service and to extend the
lifetime of the equipment
directly involving
SCADA
local monitoring and/or diagnostic
systems (
g, for power transformers)
applications for predictive assessment
of the state of equipment
performing
Event recording uploading
Analysis
And predictive assessment modeling
with key interfaces between
SCADA and historic databases
DAS and historic databases
OMS and historic databases
WMS and historic databases
Historic databases and maintenance personnel
Historic databases and contractors
with communication configuration
requirements of
WAN
LAN
Mobile
SCADA communications
Internet
with quality of service
requirements of
Frequency several times per day
with security requirements of
Authorized access
with data management requirements
of
Small to average volumes
with constraints of
New applications for predictive assessment
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
1.0 |
2.0 |
1.2 |
COMMENTS:
The following comments were collected during the team rating review:
Constraints/Concerns = 2 due to new applications for predictive assessment
D-8 Power system equipment
maintenance
The Purpose of Power
system equipment maintenance function
is to provide reliable and quality power to the
customers in the most efficient way based on reliable performance of
distribution facilities within their nominal or extended life expectancy
directly involving
Maintenance departments
Utility and contracted personnel
performing
Time and condition-based maintenance
with key interfaces between
DAS and SCADA (diagnostics)
DisCOs and TransCOs
DisCOs and RTO/ISO
DisCOs and MOS
DisCos/DAS and DER owners
DisCos and major customers
DisCos and customer representatives (serving entities)
DAS and OMS
DAS and AM/FM/GIS/CIS databases
Real-time databases and work management databases
AM/FM/GIS/CIS databases and work management databases
Maintenance field crews and DISCo databases
WMS and maintenance personnel
with communication configuration
requirements of
WAN
LAN
Internet
One-to-many
Mobile
Special media
Site with limited access
with quality of service
requirements of
Low volume data
High availability
Low frequency
with security requirements of
High security
with data management requirements
of
Timely access
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
1.0 |
2.0 |
1.0 |
2.0 |
1.6 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration =2 due to mobile computing
Security =2 due to authentication
Constraints/concerns =2 due to mobile computing
Incremental updates of the databases and consistency checking
D-8.1 Maintenance staff maintain
distribution equipment and lines
The Purpose of
Maintenance staff maintain distribution equipment and lines function
is to provide reliable and quality power to the customers in the
most efficient way based on reliable performance of distribution facilities
within their nominal or extended life expectancy
directly involving
Maintenance departments
Utility and contracted personnel
performing
Time and condition-based maintenance
with key interfaces between
DAS and SCADA (diagnostics)
DisCOs and TransCOs
DisCOs and RTO/ISO
DisCOs and MOS
DisCos/DAS and DER owners
DisCos and major customers
DisCos and customer representatives (serving entities)
DAS and OMS
DAS and AM/FM/GIS/CIS databases
Real-time databases and work management databases
AM/FM/GIS/CIS databases and work management databases
with communication configuration
requirements of
WAN
LAN
Internet
One-to-many
Mobile
Special media
Site with limited access
with quality of service
requirements of
Low volume data
High availability
Low frequency
with security requirements of
Authentication
with data management requirements
of
Timely access
with constraints of
0
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
1.0 |
2.0 |
1.0 |
1.0 |
1.4 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration =2 due to mobile computing
Security =2 due to authentication
D-8.1.1 Maintenance staff analyzes
equipment diagnostic results, compares it with the predictive models
The Purpose of
Maintenance staff analyzes equipment diagnostic results, compares it with the
predictive models function
is similar to function
(D-8.1) Maintenance staff maintain distribution equipment and lines above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
1.0 |
2.0 |
1.0 |
1.0 |
1.4 |
COMMENTS:
D-8.1.2 Maintenance staff prepares
outage requests based on time and condition criteria
The Purpose of
Maintenance staff prepares outage requests based on time and condition criteria
function
is similar to function
(D-8.1) Maintenance staff maintain distribution equipment and lines above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
1.0 |
2.0 |
1.0 |
1.0 |
1.4 |
COMMENTS:
D-8.1.3 Operations staff review and
approve outage requests
The Purpose of
Operations staff review and approve outage requests function
is similar to function
(D-8.1) Maintenance staff maintain distribution equipment and lines above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
1.0 |
2.0 |
1.0 |
1.0 |
1.4 |
COMMENTS:
D-8.1.4 Maintenance staff
identifies assets and work crew requirements
The Purpose of
Maintenance staff identifies assets and work crew requirements
function
is similar to function
(D-8.1) Maintenance staff maintain distribution equipment and lines above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
1.0 |
2.0 |
1.0 |
1.0 |
1.4 |
COMMENTS:
D-8.1.5 Work crew carries out
maintenance, coordinating with operators for switching
The Purpose of Work
crew carries out maintenance, coordinating with operators for switching
function
is similar to function
(D-8.1) Maintenance staff maintain distribution equipment and lines above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
1.0 |
2.0 |
1.0 |
1.0 |
1.4 |
COMMENTS:
D-8.2 Maintenance staff provides
information for updating relevant databases
The Purpose of
Maintenance staff provides information for updating relevant databases
function
is to timely and accurately update relevant databases in
accord with the changes implemented by the maintenance activity and verify the
correctness of the data existing in the databases
directly involving
Maintenance personnel
IT personnel
WMS
Corporate databases
performing
Preparation of forms for the maintenance personnel by the work management
personnel (system)
Completion of prepared forms by the maintenance personnel based on changes made
and parameters observed
Transmission of the forms to the relevant IT interfaces (AM/FM/GIS/Asset
management system (AMS))
with key interfaces between
Maintenance field crews and DISCo databases
WMS and maintenance personnel
with communication configuration
requirements of
WAN
LAN
Mobile communications
Internet
with quality of service
requirements of
Data accuracy
Data frequency during the major event
with security requirements of
Authentication
with data management requirements
of
Low volume
with constraints of
Incremental update of databases and consistency checking
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
1.0 |
1.0 |
1.0 |
2.0 |
1.4 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration = 2 due to mobile communications
Constraints/concerns =2 due to mobile computing
Incremental updates of the databases and consistency checking
D-8.2.1 Work crew logs activities
and results of tests
The Purpose of Work
crew logs activities and results of tests function
is similar to function
(D-8.2) Maintenance staff provides information for updating relevant databases
above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
1.0 |
1.0 |
1.0 |
2.0 |
1.4 |
COMMENTS:
D-8.2.2 Work crew identifies assets
removed and/or installed
The Purpose of Work
crew identifies assets removed and/or installed function
is similar to function
(D-8.2) Maintenance staff provides information for updating relevant databases
above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
1.0 |
1.0 |
1.0 |
2.0 |
1.4 |
COMMENTS:
D-8.2.3 Maintenance staff
identifies errors in documentation and maps
The Purpose of
Maintenance staff identifies errors in documentation and maps
function
is similar to function
(D-8.2) Maintenance staff provides information for updating relevant databases
above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
1.0 |
1.0 |
1.0 |
2.0 |
1.4 |
COMMENTS:
D-8.2.4 Maintenance staff
identifies marks up documentation ("red/green")
The Purpose of
Maintenance staff identifies marks up documentation ("red/green")
function
is similar to function
(D-8.2) Maintenance staff provides information for updating relevant databases
above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
1.0 |
1.0 |
1.0 |
2.0 |
1.4 |
COMMENTS:
D-8.2.5 Maintenance staff indicates
permanent versus temporary changes
The Purpose of
Maintenance staff indicates permanent versus temporary changes
function
is similar to function
(D-8.2) Maintenance staff provides information for updating relevant databases
above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
1.0 |
1.0 |
1.0 |
2.0 |
1.4 |
COMMENTS:
D-9 Engineering
The Purpose of
Engineering function
is to provide reliability and power quality based modern
distribution facility designs
directly involving
Distribution facility design standards
Manufacturers' information
Upgrade and new construction requirements
performing
Field inspections
Equipment specifications
Automated design
Relevant database updates (AM/FM/GIS/AMS)
Cost optimization
with key interfaces between
Engineering and other DisCo departments
DisCo and equipment manufacturers
DisCo and contractors
DisCo and builders
with communication configuration
requirements of
WAN
LAN
Internet
with quality of service
requirements of
High data accuracy and completeness (provide all necessary information for
engineering)
with security requirements of
Moderate security
with data management requirements
of
Moderate information support with transmittal of drawings
with constraints of
May need a change of legacy approach
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
COMMENTS:
D-9.1 Engineering personnel perform
distribution system engineering
The Purpose of
Engineering personnel perform distribution system engineering
function
is similar to function
(D-9) Engineering above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
COMMENTS:
D-9.2 Engineering personnel
specifies distribution power and control equipment
The Purpose of
Engineering personnel specifies distribution power and control equipment
function
is similar to function
(D-9) Engineering above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
0.0 |
COMMENTS:
D-9.3 Engineering personnel
provides information for updating relevant databases
The Purpose of
Engineering personnel provides information for updating relevant databases
function
is similar to function
(D-9) Engineering above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
COMMENTS:
D-10 Construction management
The Purpose of
Construction management function
is to timely upgrade the distribution system
directly involving
Construction department and contractors
Major customers
performing
Management and construction work
with key interfaces between
DisCO and contractor
DisCo and customers
with communication configuration
requirements of
LAN
WAN
Internet
Mobile
with quality of service
requirements of
High data accuracy
with security requirements of
Moderate security
with data management requirements
of
Moderate information support with
transmittal of drawings
with constraints of
May need a change of legacy approach
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
2.0 |
1.0 |
1.2 |
COMMENTS:
The following comments were collected during the team rating review:
Data Management = 2 due to interfacing
with asset management database
Does the comment regarding asset management correspond to the
rating of 2 for Data Management ? -- Peter Sanza -
05 Apr 2003
D-10.1 Construction managers manage
assets purchases
The Purpose of
Construction managers manage assets purchases function
is similar to function
(D-10) Construction management above.
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
2.0 |
1.0 |
1.2 |
COMMENTS:
D-10.2 Construction managers plan
construction projects
The Purpose of
Construction managers plan construction projects function
is similar to function
(D-10) Construction management above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
2.0 |
1.0 |
1.2 |
COMMENTS:
D-10.3 Construction managers manage
crew assignments
The Purpose of
Construction managers manage crew assignments function
is similar to function
(D-10) Construction management above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
2.0 |
1.0 |
1.2 |
COMMENTS:
D-10.4 Construction personnel
provides information for relevant databases
The Purpose of
Construction personnel provides information for relevant databases
function
is similar to function
(D-10) Construction management above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
2.0 |
1.0 |
1.2 |
COMMENTS:
D-11 Power Quality Management
The Purpose of Power
Quality Management function
is to
Evaluate actual power quality
Determine the sources of power quality disturbances
Provide customers with power quality needed (custom power)
Coordinate power quality with customer systems
Provide power quality reports and real time information to customers
Manage power quality in real time
Provide information for managing long term power quality
directly involving
Distribution operations
Planning
Monitoring systems
Modeling and simulation systems
Power conditioning equipment
Controlling equipment
performing
Field monitoring
Real-time modeling
Analysis and optimization of power quality
Predictive modeling
Analysis and optimization studies
Power quality focused control of distribution operations
Reporting to the customers about the utility performance
Managing power quality through interfacing customer equipment
Populating relevant databases (monitoring information
Distribution system information
Customer system information
Asset management information)
with key interfaces between
DisCo and customers
DAS and OMS
A variety of different types of permanently installed monitoring equipment and
DisCo databases
A variety of different types of temporary installed monitoring equipment and
DisCo databases
Multi-functional AMR and DisCo databases
Call in devices and DisCo databases
DAS and PQ databases
PQ management system and various corporate and real-time databases
DisCO and individual customers
DisCo and WEB servers
Lighting system and PQ database
Weather system and PQ database
SCADA and PQ database
PQ management systems and PQ database
Between different utility departments
PQ management systems and TransCo
PQ management systems and SCADA
PQ management systems and DAS
PQ management systems and equipment diagnostic systems
PQ and other corporate databases
with communication configuration
requirements of
WAN
LAN
One-to-many
Mobile
Special media
Internet
Customer communication systems
with quality of service
requirements of
High data accuracy
High data volumes
with security requirements of
Moderate security
with data management requirements
of
Large databases
Comprehensive modeling
Sophisticated optimization procedures
with constraints of
Challenge of coordinating directly with
customer systems
Challenge of optimizing system performance in the real time based on customer
priorities and conditions
New systems without significant precedent
Large databases and computation requirements
Interfaces between real time databases and system model databases
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
3.0 |
2.0 |
2.0 |
3.0 |
2.4 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration =2 due to variety of data
sources and communication systems
Service quality =3 due to high volume
data (1-5 MB/day), high data accuracy, high frequency of data transfers, high
availability, time sensitive data Security =2 due to privacy policies for PQ
data exchange with individual customers Data management =2 due to large
databases, comprehensive modeling, sophisticated optimization procedures
Constraints/Concerns =3 due to difficult-to-change legacy, challenges of new
applications and systems (
new conditioning equipment coordinated
with DRs, PQ state estimation) of data integration and recovery in case of loss
of original
(data deleted from most PQ meters after read so transfer error results in data
loss - can't read again to recover like a SCADA point misread)
D-11.1 Utility measures power
quality parameters, transmits them to central location, processes data, and
stores data in PQ database in real time
The Purpose of
Utility measures power quality parameters, transmits them to central location,
processes data, and stores data in PQ database in real time function
is to collect and manage power quality monitoring information
for entire system
directly involving
Monitoring system equipment
Distribution automation systems (DAS)
PQ
CIS and other corporate databases
performing
Monitoring
Transmitting
Processing
And storing PQ data
with key interfaces between
A variety of different types of
permanently installed monitoring equipment and DisCo databases
A variety of different types of temporary installed monitoring equipment and
DisCo databases
Multi-functional AMR and DisCo databases
Call in devices and DisCo databases
DAS and PQ databases
with communication configuration
requirements of
WAN
LAN
Internet
Mobile
Special media
Telephone systems
Customer communication systems
with quality of service
requirements of
High data accuracy
Real time data collection
High data volume
with security requirements of
Limited disclosure
with data management requirements
of
Large databases
with constraints of
Diversity of data structures
Existing infrastructures and databases for separate monitoring systems must be
incorporated into a common system for overall data collection and database
management
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
3.0 |
1.0 |
2.0 |
2.0 |
2.0 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration =2 due to variety of data
sources and communication systems
Service quality =3 due to high volume data (1-5 MB/day)
High data accuracy
High frequency of data transfers
High availability
Time sensitive data
Data management =2 due to large databases
Comprehensive modeling
Sophisticated optimization procedures
Constraints/Concerns =2 due to challenges of data integration and recovery in
case of loss of original measurements
D-11.2 Real time power quality
state estimation system calculates power quality characteristics based on
limited monitoring information from substations, distribution systems, and
customer systems and models (pseudo-measurements) supplementing to the needed
redundancy
The Purpose of
Real time power quality state estimation system calculates power quality
characteristics based on limited monitoring information from substations,
distribution systems, and customer systems and models (pseudo-measurements)
supplementing to the needed redundancy function
is to
In addition to the DA applications
Expands the value of power quality monitoring (especially for higher harmonics
and rapid transient processes) by calculating the power quality levels
throughout the system using a combination of limited monitoring information and
models of the electrical system
Providing reasonable estimates of the power quality characteristics and
relationships
directly involving
Real time monitoring systems
PQ databases
Real time database of system electrical characteristics
Modeling and optimization algorithms
performing
State-estimation like procedures based
on simulation and optimization algorithms
with key interfaces between
PQ management system and various
corporate and real-time databases
with communication configuration
requirements of
WAN
LAN
Internet
Mobile
Special media
Telephone systems
Customer communication systems
with quality of service
requirements of
High data accuracy
Real time data collection
High data volume
with security requirements of
Limited disclosure
with data management requirements
of
Large databases of monitoring data
combined with databases describing system electrical system configuration and
characteristics
with constraints of
System models incorporate a wide
variety of components (GIS
Load characteristic models
Including higher frequencies component
Short circuit models
Load flow models
Including for higher harmonics
Equipment databases), that must be combined for real time state estimation
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
3.0 |
1.0 |
2.0 |
3.0 |
2.2 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration =2 due to variety of data
sources and communication systems
Service quality =3 due to high volume
data (1-5 MB/day), high data accuracy, high frequency of data transfers, high
availability, time sensitive data Data management =2 due to large databases,
comprehensive modeling, sophisticated optimization procedures
Constraints/Concerns =3 due to difficult-to-change legacy, challenges of new
applications and systems (
new conditioning equipment coordinated
with DRs, PQ state estimation)
D-11.3 Utility exposes historical
and real-time power quality data to customers
The Purpose of
Utility exposes historical and real-time power quality data to customers
function
is to provide real time and statistic PQ Information to
customers
directly involving
PQ databases
Communication systems
Customers
performing
Selection of customer-customized data
of power quality following privacy policies and preparation of general
performance characteristics for all customers of the utility
with key interfaces between
DisCO and individual customers
DisCo and WEB servers
with communication configuration
requirements of
LAN
Internet
Telephone systems
with quality of service
requirements of
Real time access to the PQ monitoring
database
Data accuracy
Data volumes
with security requirements of
Authentication and security for
customers to access their own PQ data
with data management requirements
of
Individual customer based
with constraints of
Legacy reluctance of the utilities to
provide access to this type of database information
New applications
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
2.0 |
2.0 |
1.0 |
2.0 |
1.6 |
COMMENTS:
The following comments were collected during the team rating review:
Service quality = 2 due to high volume
data
High data accuracy
High frequency of data transfers
High availability
Time sensitive data
Security =2 due to privacy policies for PQ data exchange with individual
customers
Constraints/Concerns =2 due to difficult-to-change legacy
Challenges of new applications
D-11.4 Utility correlates data from
utility operations database, lightning database, and other operations related
database with PQ event database and generates reports and/or stores analysis
results for future reporting
The Purpose of
Utility correlates data from utility operations database, lightning
database, and other operations related database with PQ event database and
generates reports and/or stores analysis results for future reporting
function
is to automatically identify cause and possible impacts for
different disturbances and conditions on PQ
directly involving
Weather systems
Lighting systems
SCADA disturbance monitoring system
SOE systems
Event recorders
PQ monitoring systems and database
performing
Correlation of disturbances with power
quality characteristics
with key interfaces between
Lighting system and PQ database
Weather system and PQ database
SCADA and PQ database
PQ management systems and PQ database
with communication configuration
requirements of
WAN
LAN
Internet
Mobile
Special media
Telephone systems
Customer communication systems
with quality of service
requirements of
Timely availability
Data volumes during major events
Data frequency during limited time
with security requirements of
Low level
with data management requirements
of
Coordination of data according relevant
associations
with constraints of
Different multiple systems and access
requirements
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
3.0 |
1.0 |
2.0 |
2.0 |
2.0 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration =2 due to variety of data
sources and communication systems
Service quality =3 due to high volume data
High frequency of data transfers
High availability
Time-synchronization sensitive data
Data management =2 due to large databases and data coordination
Constraints/Concerns =2 due to challenges of data integration from different
systems
D-11.5 The utility PQ evaluation
system analyzes PQ events, trends, and profiles of power quality levels of the
supply system against planning limits and operation objectives. The system is
used to generate recommendations and priorities for system improvements
The Purpose of
The utility PQ evaluation system analyzes PQ events, trends, and profiles of
power quality levels of the supply system against planning limits and operation
objectives. The system is used to generate recommendations and priorities for
system improvements function
is to provide power quality performance reports for use in
distribution planning and asset management
directly involving
Distribution planning
Asset management
And maintenance personnel
performing
Performance reports focused on
prioritizing system improvements, that can improve power quality levels
with key interfaces between
Between different utility departments
with communication configuration
requirements of
LAN
Internet
with quality of service
requirements of
Availability of access to power quality
monitoring database along with functions to evaluate effect of system
improvements on expected power quality levels in the future
with security requirements of
Low level
with data management requirements
of
Several databases
with constraints of
Difficult to change legacy approach
(power quality has generally not been considered in the past for prioritizing
maintenance and system improvements)
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
COMMENTS:
D-11.6 The power quality management
system analyzes PQ events and profiles to identify causes of PQ problems and
possible equipment problems that could be corrected. Detailed recommendations
are developed and automatic responses are implemented where possible
The Purpose of The
power quality management system analyzes PQ events and profiles to identify
causes of PQ problems and possible equipment problems that could be corrected.
Detailed recommendations are developed and automatic responses are implemented
where possible function
is to
automatically identify possible
equipment problems and operational problems based on power quality event
characteristics (
breaker problems, arrester problems, transformer problems, capacitor problems,
cable insulation problems, line problems such as lines slapping together,
regulator problems
)
directly involving
Distribution operations systems
Asset management systems
Power quality monitoring database
Equipment diagnostic systems and databases
performing
Analysis and reporting of possible
equipment problems
Recommendations for DA system to implement remedial measures where possible
with key interfaces between
PQ management systems and TransCo
PQ management systems and SCADA
PQ management systems and DAS
PQ management systems and PQ databases
PQ management systems and equipment diagnostic systems
with communication configuration
requirements of
WAN
LAN
SCADA communications
with quality of service
requirements of
Real time availability of monitoring
data and equipment status information for evaluation in expert systems and
timely identification of possible problems
with security requirements of
Low level
with data management requirements
of
Several databases (monitoring database
Equipment databases
Expert systems)
Timely access
with constraints of
Configuration of expert systems to
identify equipment problems requires extensive monitoring and correlation of
problems with actual events
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
COMMENTS:
D-11.7 The power quality
information is evaluated with respect to specific customer requirements on the
specific system. Coordination with equipment and power conditioning equipment
within customer facilities is implemented to improve productivity and
reliability of customer systems. (See description in Customer Services Domain)
The Purpose of The
power quality information is evaluated with respect to specific customer
requirements on the specific system. Coordination with equipment and power
conditioning equipment within customer facilities is implemented to improve
productivity and reliability of customer systems. (See description in Customer
Services Domain) function
is similar to function
(D-11) Power Quality Management above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
3.0 |
2.0 |
2.0 |
3.0 |
2.4 |
COMMENTS:
D-11.8 Utility accesses PQ database
and generates bill/refund/penalty statement for events that exceed contract
limits. (see description in the Customer Services Domain)
The Purpose of
Utility accesses PQ database and generates bill/refund/penalty statement for
events that exceed contract limits. (see description in the Customer Services
Domain) function
is similar to function
(D-11) Power Quality Management above.
On a scale of 0 (does not involve significant
architectural challenges) to 3 (highly likely
to involve architectural challenges) this function was rated as
follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
3.0 |
2.0 |
2.0 |
3.0 |
2.4 |
COMMENTS:
D-11.9 Utility generates various
reports from PQ database for operation, management, engineering, and customer
consumption via e-mail and web interfaces
The Purpose of
Utility generates various reports from PQ database for operation, management,
engineering, and customer consumption via e-mail and web interfaces
function
is to reporting on power quality conditions and
causes/effects
directly involving
Management
Distribution planning
Distribution operations
Marketing
Customers
performing
Summary analyses of large databases of
information in useful forms for decision making and assessment and preparation
of reports of power quality conditions for use in assessing system performance
Power quality impacts
Economic impacts
And improvement alternatives
with key interfaces between
PQ and other corporate databases
with communication configuration
requirements of
WAN
LAN
Internet
with quality of service
requirements of
Availability
with security requirements of
Limited disclosure
with data management requirements
of
Using large power quality monitoring
databases and integrating results of intelligent analysis systems
State estimation systems
And equipment effect analysis
Etc
with constraints of
Needs of understanding of economic
issues associated with PQ parameters, as well, as technical issues
And r importance of impacts of power quality conditions
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
1.0 |
COMMENTS:
D-12 Dispatcher Training Simulator
The Purpose of
Dispatcher Training Simulator function
is to
Provide the distribution operation
personnel with a comprehensive training means to analyze a variety of
practically possible operating conditions
The individual and coordinated behavior of the distribution automation systems
The interrelationships of different operational parameters
The role of information support of the computing applications
And the user interfaces of the systems in use
directly involving
The operation
Operation planning
DAS maintenance personnel
SCADA
DAS
OMS
WMS
AM/FM systems
performing
"what if" studies of the distribution
system operation based either on real-time information or on other base-cases
with key interfaces between
DTS and SCADA/DA
DTS and MOS
DTS and OMS
DTS and AM/FM/GIS/CIS databases
DTS and WMS
DTS and other Utility Departments
with communication configuration
requirements of
WAN
LAN
Internet
with quality of service
requirements of
Transferring large volumes of data
with security requirements of
Limited disclosure
with data management requirements
of
Creating large models combining
existing models with hypothetical scenarios without disrupting the operations of
the automated systems in production
with constraints of
New sophisticated applications
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
1.0 |
1.0 |
1.0 |
2.0 |
3.0 |
1.6 |
COMMENTS:
The following comments were collected during the team rating review:
Data Management =2 due to combination
of data of different time frames
Constraints/Concerns =3 due to the need to develop new sophisticated
applications
D-13 Distribution Asset Management
The Purpose of
Distribution Asset Management function
is to store asset information in one centralized database
providing access to all relevant parties
directly involving
System planners
Engineers
Operation personnel
Maintenance personnel
Construction personnel
Power quality personnel
IT personnel
performing
Recording of asset data
Up-front consistency checking
Updating records
Adding and cloning new assets
Submitting defaults
Asset tracking
Sorting
Filtering
Finding required information about assets
Identifying trends in asset usage and replacement
Monitoring maintenance periodicity
Contract progress
And life cycles of assets
Alarming and announcement about asset conditions
Generating reports
Providing total and incremental extracts for different users
Output consistency checking
Preparing forms for different input data providers
Etc
with key interfaces between
Asset Management System (AMS) and other
utility departments
AMS and DAS
AMS and PQ database
AMS and OMS
AMS and WMS
with communication configuration
requirements of
WAN
LAN
Mobile
Internet
One-to-many
with quality of service
requirements of
Availability
Data accuracy
Data volumes
with security requirements of
Authentication
Access Control
Information Integrity
Confidentiality
with data management requirements
of
Large database
Timely update
Timely access
with constraints of
Difficult-to-change legacy system
New applications
On a scale of 0 (does not involve significant architectural
challenges) to 3 (highly likely to involve
architectural challenges) this function was rated as follows:
Configuration |
Quality of Service |
Security |
Data Management |
Constraints |
Average |
2.0 |
2.0 |
2.0 |
3.0 |
3.0 |
2.4 |
COMMENTS:
The following comments were collected during the team rating review:
Configuration = 2 due to different
communication systems
Quality of service = 2 due to accuracy
Data volumes
Security = 2 due to access control
Confidentiality
Data management= 3 due to large database
Timely update and access
Constraints = 3 due to need of significant changes in existing databases to
accommodate new applications