Event |
Name of Process/Activity
|
Description of
Process/Activity |
Information Producer
|
Information
Receiver |
Name of Info Exchanged
|
IntelliGrid Architecture Environments
|
1 |
On-going |
Submit energy schedules |
(1)
Submit Balanced Energy Schedules,
including self-provided Ancillary
Services Schedules, any inter-SC trades,
and any generation limit changes, until
Schedule Close |
Scheduling Coordinators |
Market
Interface Web Server |
Energy schedules |
RTOs/Market Participants |
2 |
Submittal of an energy schedule |
Validation |
(2)
Indicates valid input or indicates
clerical & format errors |
Market
Interface Web Server |
Scheduling Coordinators |
Energy schedules |
RTOs/Market Participants |
3 |
Correction |
Correction |
(3)
Corrects errors |
Scheduling Coordinators |
Market
Interface Web Server |
Energy schedules |
RTOs/Market Participants |
4a |
Valid energy schedule submitted |
Energy Schedule Analysis |
(4a)
Provides Day-Ahead Energy Schedules |
Market
Interface Web Server |
Energy
Schedule Analysis |
Energy schedules |
RTOs/Market Participants |
4b |
Simultaneous with previous step |
Energy Schedules to RTOs |
(4b)
Provides Day-Ahead Energy Schedules
relevant to each RTO |
Market
Interface Web Server |
Other 2
RTOs Energy Schedule Processing |
Energy schedules |
RTOs/Market Participants |
5a |
Analysis of energy schedules |
Adjustment to energy schedules |
(5a)
Adjusts any unbalanced schedules and
stores validated input as proposed
schedules |
Energy
Schedule Analysis |
RTO
Energy & A/S Schedules |
Energy schedules |
Intra-Control Center |
5b |
Simultaneous with previous step |
Adjusted energy Schedules to RTOs |
(5b)
Provides adjusted and validated
cross-RTO schedules |
Energy
Schedule Analysis |
Other 2
RTOs Energy Schedule Processing |
Energy schedules |
RTOs/Market Participants |
5c |
Simultaneous with previous step |
Apply existing energy schedule contracts |
(5c)
Enter existing contracts |
Existing
Transmission Contracts |
RTO
Energy & A/S Schedules |
Existing energy schedule contracts |
Intra-Control Center |
6a |
Day Ahead Market Close |
Time-based trigger |
(6a)
Initiates Day Ahead security analysis
verification after Schedule Close |
Time Line
Manager Function |
Congestion Management Function |
Day Ahead Energy schedules |
Intra-Control Center |
6b |
Simultaneous with previous step |
Retrieve Day-Ahead schedules |
(6b)
Retrieves all Day Ahead schedules |
RTO
Energy & A/S Schedules |
Congestion Management Function |
Day Ahead Energy schedules |
Intra-Control Center |
6c |
Simultaneous with previous step |
Cross-RTO security analysis |
(6c) For
cross-RTO schedules, validates
schedules, adjusts any unbalanced
schedules, and provides as proposed
schedules |
Other 2
RTOs Energy Schedule Processing |
RTO
Energy & A/S Schedules |
Day Ahead Energy schedules |
RTOs/Market Participants |
7a |
After previous step |
Security Analysis |
(7a)
Verifies schedules meet intra-zonal &
connection point security requirements |
Congestion Management Function |
RTO
Energy & A/S Schedules |
Day Ahead Energy schedules |
Intra-Control Center |
7b |
Simultaneous with previous step |
Cross-RTO security analysis |
(7b) For
cross-RTO schedules, provide results of
Congestion Management analysis |
Congestion Management Function |
Other 2
RTOs Energy Schedule Processing |
Day Ahead Energy schedules |
RTOs/Market Participants |
8a |
After previous step |
Post results of security analysis |
(8a)
Posts results of Congestion Management
analysis of schedules |
RTO
Energy & A/S Schedules |
Market
Interface Web Server |
Day Ahead Energy schedules |
RTOs/Market Participants |
8b |
Simultaneous with previous step |
Post results of cross-RTO security analysis |
(8b)
Posts results of Congestion Management
analysis of cross-RTO schedules |
Other 2
RTOs Energy Schedule Processing |
Market
Interface Web Server |
Day Ahead Energy schedules |
RTOs/Market Participants |
8c |
Simultaneous with previous step |
Cross-RTO conflicts |
(8c)
Notify of cross-RTO conflicts or
inconsistencies |
Other 2
RTOs Energy Schedule Processing |
RTO
Scheduler |
Cross-RTO conflicts |
RTOs/Market Participants |
9 |
After step 8c |
Resolve cross-RTO conflicts |
(9) Posts
resolutions to cross-RTO conflicts and
inconsistencies |
RTO
Scheduler |
Market
Interface Web Server |
Resolved cross-RTO conflicts |
RTOs/Market Participants |
10 |
After previous step |
Notify Scheduling Coordinators |
(10)
Notifies of schedule acceptances and
rejections |
Market
Interface Web Server |
Scheduling Coordinators |
Accepted Energy schedules |
RTOs/Market Participants |
11 |
Upon request by Scheduling Coordinators |
Revisions to energy schedules |
(11)
Enter revisions to schedules as needed,
until Revision Close |
Scheduling Coordinators |
Market
Interface Web Server |
Revised energy schedules |
RTOs/Market Participants |