Long Term Planning - Market Operations

Narrative

Overview

As the electricity industry is deregulated, and as FERC defines more clearly what the market operation tariffs will encompass, three possible Regional Transmission Organizations (RTOs) in the Western Interconnection are developing seamless interfaces for Market Participants to submit energy schedules and ancillary service bids across these 3 RTOs. The 3 RTOs are California ISO (existing ISO handling the electricity market in California), RTO West (potential RTO of many northwestern utilities), and WestConnect (potential RTO of many southwestern utilities). These 3 RTOs are developing the requirements for the Western RTO functions.

Description

The following is a list of Western RTO functions related to long term planning for market operations. Only the listed functions with asterisks are represented in the diagrams and/or step-by-step descriptions in section 2. The others are either subsets of the functions or are not primarily an automated function.

1.        Long Term Planning

a.        Registration of Market Participants

·         Credit rating of Market Participants

b.       Capacity/Adequacy Market

c.       Updating the Power System Model for ISO/RTO Regional Planning*

·         Register transmission data with WSCC EHV database

·         Perform WSCC path studies

·         Perform grid assessment

·         Perform new generation connection studies

·         Perform RMR studies

d.        Transmission and Generation Maintenance Coordination *

·         Establish transmission and generation standards and guidelines

·         Oversee ISO grid planning

e.        Generation certification

Power System Model Update (PSMU) for ISO/RTO Regional Expansion Planning

The purpose of ISO/RTO: Regional Expansion Planning function is to develop load and capacity forecast alternatives, by collecting load and capacity forecasts from different market participants inside and outside the region, developing regional and local alternatives of load and capacity, including coordination with customers with special loads and/or generation capabilities. Also coordinating transmission system planning submitted by transmission owners, developing future regional power system model alternatives, calculating and publishing future major operational parameters for the expansion alternatives, and developing requirements for system automation., directly involving RTO/ISO planners, Generation planners, DR planners, transmission planners, distribution planners, regulators, auditors, regional planning agencies, Special Customers, NERC, and Market Participants, performing regional, long term load and capacity planning and coordination of other planners within the region, including long term adequacy and reliability analysis via studies to assist in market decisions, with key interfaces between:

1. RTO/ISO and other RTOs

2. RTO and Transmission Owners

3. RTO and Generation Companies

4. RTO and DisCos

5. RTO and Special Customers

6. RTO and Security Coordinating Councils

7. RTO and NERC

8. RTO and Regulators

9. RTO and Auditors

10. RTO and Planning Agencies

11. RTO and Government offices,

 

#

Event

Name of Process/Activity

Description of
Process/Activity

Information Producer

Information
Receiver

Name of Info Exchanged

IntelliGrid Architecture Environments

1.1a

Periodically or as needed

Update power system model

Provide updated transmission facilities model data and in-service dates

Transmission Owner

Power System Model

Transmission facilities

Inter-Control Center

1.1b

Periodically or as needed

Update power system model

Provide updated generation facilities model data and in-service dates

GenCos

Power System Model

Generation facilities

Inter-Control Center

1.1c

Periodically or as needed

Update power system model

Provide updated connection point model data and in-service dates

DisCos

Power System Model

Distribution facilities

Inter-Control Center

1.1d

Periodically or as needed

Update power system model

Provide updated connection point model data and in-service dates

Eligible Customers

Power System Model

Customer facilities

Control Center/ Corporations

1.1e

Periodically or as needed

Update power system model

Provide updated transmission facilities model data and in-service dates

WSCC

Power System Model

WSCC transmission facilities

Inter-Control Center

1.1f

Periodically or as needed

Update power system model

Provide updated transmission facilities model data and in-service dates

RTO Power System Model

Power System Model

Other RTO transmission facilities

Inter-Control Center

1.2

Periodically or as needed

Review updates

Review updates

Power System Model

RTO Programmer Engineer Personnel

Updates

Intra-Control Center

1.3

After previous step

Review power model

Assure completeness and accuracy of updated model

RTO Programmer Engineer Personnel

Power System Model

Power System model

Intra-Control Center

1.4a

After previous step

Issue updated power system model

Issue updated power system model

Power System Model

Eligible Customers

Power System model

Control Center/ Corporations

1.4b

After previous step

Issue updated power system model

Issue updated power system model

Power System Model

DisCos

Power System model

Inter-Control Center

1.4c

After previous step

Issue updated power system model

Issue updated power system model

Power System Model

GenCos

Power System model

Inter-Control Center

1.4d

After previous step

Issue updated power system model

Issue updated power system model

Power System Model

Transmission Owner

Power System model

Inter-Control Center

1.4e

After previous step

Issue updated power system model

Issue updated power system model

Power System Model

WSCC

Power System model

Inter-Control Center

1.4f

After previous step

Issue updated power system model

Issue updated power system model

Power System Model

RTO Power System Model

Power System model

Intra-Control Center

 

Maintenance Coordination Function (MC) for Transmission System Planning

The purpose of Transmission Owners/Distribution Utilities: System Planning function is to develop transmission and distribution facility plans for the long term, based on load and capacity forecasts, RTO or other regional plans, regulator requirements, neighboring utility requirements, and customer requirements. In addition to facility plans, detailed automation plans will be developed, directly involving transmission data, distribution data, generation planners, customers, DR planners, regulators, auditors, vendors, regional planning agencies, and government agencies, performing long term transmission and distribution facilities and automation planning, with key interfaces between

1. TransCos and RTOs

2. TransCos and neighboring utilities

3. TransCos and generation companies

4. TransCos and DR owners

5. TransCos and planning agencies

6. TransCos and large customers

7. TransCos and government agencies,

 

#

Event

Name of Process/Activity

Description of
Process/Activity

Information Producer

Information
Receiver

Name of Info Exchanged

IntelliGrid Architecture Environments

2.1a

Periodically or upon event

Submit outage schedules

(1a) Submit relevant proposed transmission outage schedules

Other 2 RTOs

Transmission Outage Schedule

Transmission outage schedules

RTOs/Market Participants

2.1b

Periodically or upon event

Submit outage schedules

(1b) Submit long term proposed transmission outage schedules

Transmission Owner

Transmission Outage Schedule

Transmission outage schedules

Inter-Control Center

2.1c

Periodically or upon event

Submit outage schedules

(1c) Submit long term proposed Local Generation Resources (LGR) generation maintenance schedules

GenCos

LGR Generation Maintenance Schedule

Generation maintenance schedules

Inter-Control Center

2.2a

After previous step

Analyze outage schedules

(2a) Provide proposed transmission outage schedules

Transmission Outage Schedule

Maintenance Outage Function

Transmission outage schedules

Inter-Control Center

2.2b

 

Analyze maintenance schedules

(2b) Provide proposed generation maintenance schedules

LGR Generation Maintenance Schedule

Maintenance Outage Function

Generation maintenance schedules

Inter-Control Center

2.2c

 

Provide power system model

(2c) Provide Base Case model

Power System Model

Maintenance Outage Function

Power system model

Intra-Control Center

2.2d

 

Provide load forecast

(2d) Provide LT Load Forecast

Long Term Load Forecast

Maintenance Outage Function

Load forecast

Intra-Control Center

2.2e

 

Provide energy schedules

(2e) Provide all schedules already submitted by Scheduling Coordinator and all existing contracts

Energy Schedule Database

Maintenance Outage Function

Energy schedules

Intra-Control Center

2.3

At specific time and date

Determine acceptable schedules

(3) Once a month on a specific day, work with maintenance outage requests to determine acceptable outage schedules

Maintenance Outage Function

RTO Scheduler

Outage schedules

User Interface

2.4a

After previous step

Accept transmission outage schedule

(4a) Accept transmission outage schedule

RTO Scheduler

Transmission Outage Schedule

Accepted transmission outage schedules

User Interface

2.4b

 

Reject transmission outage schedule

(4b) Reject transmission outage schedule

RTO Scheduler

Transmission Outage Schedule

Rejected transmission outage schedules

User Interface

2.4c

 

Accept generation maintenance schedule

(4c) Accept generation maintenance schedule

RTO Scheduler

LGR Generation Maintenance Schedule

Accepted generation maintenance schedules

User Interface

2.4d

 

Reject generation maintenance schedule

(4d) Reject generation maintenance schedule

RTO Scheduler

LGR Generation Maintenance Schedule

Rejected generation maintenance schedules

User Interface

2.5a

After previous step

Transmission outage scheduling results

(5a) Receive acceptance or warning on transmission outage schedule

Transmission Outage Schedule

Other 2 RTOs

Outage scheduling results

RTOs/Market Participants

2.5b

 

Transmission outage scheduling results

(5b) Receive acceptance or rejection of transmission outage schedules

Transmission Outage Schedule

Transmission Owner

Outage scheduling results

Intra-Control Center

2.5c

 

Generation maintenance results

(5c) Receive acceptance or rejection of LGR generation maintenance schedules

LGR Generation Maintenance Schedule

GenCos

Generation maintenance schedule results

Inter-Control Center

 

 

 

 

 