This section presents the conclusions resulting from the development process that took place during the past 18 months. The conclusions are divided into two sections:

§       A summary of how IntelliGrid Architecture hopes to satisfy the industry drivers.

§       A commentary by the project team on the results and the process used to develop them.

The Initial Steps Have Been Taken: Satisfying Industry Drivers

IntelliGrid Architecture was an endeavor to address a set of industry drivers. Specifically, how has the effort addressed these drivers?

Driver 1: Cost effective use of emerging technology

With its emphasis on incremental deployment of applications within a framework of interoperable boundaries, IntelliGrid Architecture provides the ability to add functionality without a requisite construction of infrastructure. Yet, as applications cross boundaries they can fuse with others without significant re-engineering, as is the case with today’s technical islanding approach.

Driver 2: Higher levels of integration across traditional boundaries

The IntelliGrid Architecture has validated the original hypothesis of the energy industry needing higher levels of integration.  This was in part validated by requirements gathered within this project as well as by one of the most significant events that occurred in the electric industry's history. The August 14, 2003 blackout brought to the surface many of the technical issues that are directly addressed in IntelliGrid Architecture project and recommendations.

Driver 3: Infrastructure development and standards coordination

The initial steps have been taken to match emerging stakeholder requirements with emerging and developing standards and infrastructure.   Many of the key standards and related technologies as well as other key infrastructure elements that can be used as part of an overall industry infrastructure are in development and emerging today.  Project recommendations summarized here and presented in greater depth in other volumes point to these technologies based on their ability to satisfy architectural level requirements.  More work is required however to bring them into full use to meet the demanding needs of future advanced automation systems.  

Driver 4: Responding to new and emerging requirements

By providing a framework for applications integration and development, IntelliGrid Architecture provides an ongoing repository for requirements adoption and refinement. By concentrating at the abstract level of IntelliGrid Architecture, such requirements can be dovetailed into a growing infrastructure with minimal perturbation of previous applications.

Driver 5: Industry visioning and enabling a robust future

This section briefly reiterates the basic principles of the architecture.  The IntelliGrid Architecture is based on state-of-the-art communications concepts and trends in information engineering, stemming from:

§       The description and analysis of communication and information requirements of power system operational functions

§       The use of system and data modeling to capture and analyze these requirements

§       The definition of utility-specific environments having common sets of requirements

§       The use of layered technologies to separate levels of abstraction and functionality

§       The use of common services, information models, and technology-independent interfaces to create an architecture that is not dependent on one set of technologies.

§       The recommendation of specific standard technologies and best practices that can meet the power system architectural requirements

§       The identification of missing or overlapping technologies as a tool for making technology recommendations.

Commentary on the Process

This section provides the qualitative conclusions of the project team regarding the results of IntelliGrid Architecture project and the process used to develop them. Those preparing to continue the work on IntelliGrid Architecture or develop similar projects may find these conclusions useful.

The IntelliGrid Architecture team was challenged at the outset to devise a starting point for an energy industry architecture that could evolve, grow, and mesh with the efforts of architecture work in other spheres of commerce and communications. In this time of rapid technological evolution and insertion of communications into every aspect of energy delivery and use, it was necessary to grab a toehold so that projects incorporating communications technologies could have a path towards integration. It is easy for an office worker to upgrade his or her technology with a replacement computer every two or three years. Yet, with capital-intensive facilities such as those operated for the generation, transport, and use of energy, a far longer-term perspective is required.

With these two conflicting goals juxtaposed, IntelliGrid Architecture project was funded and directed to accomplish its work in an 18-month timeframe. Why 18 months? Because a shorter timescale would preclude serious in-depth work, and, a longer timescale would come too late to be useful.

The IntelliGrid Architecture team endeavored to take a systems engineering approach to distilling stakeholder requirements into an architecture definition.  Due to the large scope of the project, the team focused their efforts in certain areas. These focuses and other observations are summarized in the sections that follow. They are described in roughly the order they were encountered in the project.

All in all, the team believes that an appropriate balance was indeed achieved in the varied activities of the project. Obviously, time will tell whether this is correct, and, we will have to observe the application and extension of IntelliGrid Architecture to ultimately judge these choices.

Depth vs. Breadth

During Task 1, the team sought to identify an appropriate goal for coverage of utility operations for the project. We quickly found that the most architecturally interesting future applications for the industry involved transfer of information across departmental and institutional boundaries, and especially, involved varied interactions with customers. The team agreed that if we studied the communications requirements of these cross-organizational types of applications, we could identify most significant industry requirements. This is especially true because those communications that remain within a constrained environment are already well understood and often covered by well-documented industry standards and art.

The IntelliGrid Architecture project was able to study communications requirements from markets to consumers, from power plants to substations and pole-tops, and permutations of this breadth. For depth, the applications were studied with a primary focus on the identification of the participants in communications, the kinds of information exchanged, and, the simplified exchange sequences that would typify such applications.

To bring the applications that were reviewed in this manner to the point where the documentation fully specifies an implementation would require several additional levels of detail. It would be necessary for the models of data to be exchanged and all the details of the exchange sequences, fault accommodation and recovery, etc. to be captured. As noted elsewhere in the Conclusions and Recommendations, IntelliGrid Architecture is an ongoing process, and further development of the depth of analysis would be very useful.

Stakeholder Requirements

A pure systems engineering approach to any problem will use stakeholder engagement to obtain requirements from potential users and providers of services. Systems architects then analyze these requirements in a formal process to identify commonality of need and the technically detailed design requirements they imply.

In IntelliGrid Architecture project, stakeholder requirements were captured primarily through the development of a document called the ‘Domain Template’. This document and process were designed to obtain detailed information from ‘domain experts’ so we could obtain a quantitative view of industry application requirements. This process is described in Volume II.

While we had great success in obtaining entrée to those experts in the industry that could provide us with input, these same experts had very limited time with which to devote on our behalf. Therefore, in most cases we first populated a series of Domain Templates from the knowledge and experience of the members on the team. We then presented these for discussion with industry experts to refine their content. In a few instances, we were actually able to obtain full Domain Templates from specific stakeholders, but these cases were not very common

It would therefore be desirable to populate a greater number of Domain Templates. While the project applied the 80/20 rule, the last 20% of potential applications can be expected to introduce some new concepts. This will be recommended for future work.

Functional Requirements Analysis

The IntelliGrid Architecture Domain Template incorporates a detailed spreadsheet. This spreadsheet identifies hundreds of potential architectural requirements that are evaluated by the analyst for each of the specific steps in the implementation scenario being described.

This analysis was time consuming and proved to be beyond the effort that the stakeholders were able to invest. Therefore, based on the engagement interviews, members of IntelliGrid Architecture team performed this analysis on most of the Domain Templates. Several of these spreadsheets were not completed, and it would be desirable to complete this in the future.

Mapping to UML

The requirements were represented in the Domain Template in the form of a natural language document and an analysis spreadsheet. The template was arranged to have a careful and specific correspondence to RM-ODP constructs, the methodology adopted by the team. These same constructs were then represented in UML using an automated tool, for import into the Magic Draw modeling tool.

It is possible to achieve several roughly equivalent mappings that make logical sense in UML. Ultimately, the team chose an approach that would optimize the match between the modeling tool, the feature set of the Domain Templates, and the relationships we wanted to preserve. The team was able to achieve a substantially satisfying result in this manner. The resulting model carefully preserves all of the semantics obtained through the Domain Template capture and analysis process, and provided an explicit means to correlate actors, information objects, data exchanges, requirements, services, environments, and technologies

However, we used more of a reliance on tagged values (a UML extension mechanism) than we would have desired, due to their unique ability to hold multi-valued constraints (a technical but important detail). In the future, we might prefer to use UML constraints rather than tagged values because they explicitly describe constraints on interfaces, objects and methods.

Template Import

The templates were designed to be self contained and populated by independent individuals and groups. After they were internally complete, a normalization process was used to make the nomenclature used in the various templates consistent with each other. This process of normalization tended to be time consuming since the many objects identified in each template – actors, information objects, etc. needed to be compared to similar ones from other templates. A from/to list had to be constructed and the results reviewed to ensure consistency and sanity of the results.

Although tedious, this was considered a preferable approach to trying to coordinate all template population efforts to use a consistent nomenclature while the nomenclature was being discovered through the engagement process. However, in the future, the extensive list of names (terms) identified can be used in subsequent uses of the template as a suggested list to avoid redundant creations.

Parallel Studies

While the stakeholder engagement process was expected to derive substantial requirements from an application standpoint, the team believed that it was necessary to perform a parallel investigation into general topics such as security and network management, and, the relationship of IntelliGrid Architecture to other architectures. This analysis was able to produce the next level of detailed requirements that are beyond the scope of most stakeholders, yet crucial to the proper operation of a distributed computing environment.

The IntelliGrid Architecture model of services first relies on a set of simple primitives. These primitives can be combined to allow high level services to be described. In the course of the project, it was possible to identify an extensive set of high level abstract services and to somewhat represent their relationship to architectural elements of IntelliGrid Architecture. However, there was not sufficient time to apply these high-level services to the individual steps in the Domain Template scenarios as would be desirable. All the necessary information is in fact in IntelliGrid Architecture model to permit this to be done.  It is suggested that this might be a desirable component of future work.

Aggregation of Atomic Requirements

The requirements that were filled out in the spreadsheets associated with the Domain Template were termed the atomic requirements/questions because they were formed as questions using terms that would be familiar to power system engineers. These 400 atomic requirements/questions were therefore combined into 63 Aggregated Requirements that more clearly identified the architectural requirements. Examples of this mapping from atomic requirements/questions to Aggregated Requirements are:

§       “Are the distances between communicating entities a few to many miles?” plus “Location of information producer (source of data) is outside substation, or another corporation or a customer site while the Location of the information receiver is outside a substation, or another corporation or a different customer site” became the Aggregated Requirement to “Support interactions across widely distributed sites”

§       “Eavesdropping: Ensuring confidentiality, avoiding illegitimate use of data, and preventing unauthorized reading of data, is crucial” plus “Information theft: Ensuring that data cannot be stolen or deleted by an unauthorized entity is crucial” became the Aggregated Requirement “Provide Confidentiality Service (only authorized access to information, protection against eavesdropping)”

Development of IntelliGrid Architecture Environments

During the analysis of the communication and information requirements of the power system functions, it became clear that the nature of these requirements depend upon a few factors:

§       Locations of the entities exchanging information: some were within a particular site, while some involved inter-site exchanges

§       The response times and availability required by the functions: some required very rapid, deterministic information flows, while others had less stringent constraints

§       The criticality of the information: some information flows were very critical to reliable and safe power system operations, while others had less impact

§       Organizational boundaries: some information remained within one organization, while other information flows involved multiple organizations

Atomic Requirements Approach. The atomic requirement correlations were analyzed against technologies and services in spreadsheets and the resulting relationships were imported into the UML model in order to provide a complete integrated object model. The IntelliGrid Architecture team is made up of primarily energy industry domain experts. As such the perspective and experience of these members is a necessary and valuable ingredient in the knowledgeable analysis of the data. However, in order to minimize bias in this analysis, the correlations were captured at a more or less ‘microscopic’ level – that of the individual requirements. This process is based on the idea that if technologies are correlated to individual requirements, and the environments are correlated to the same requirements, there will be a best fit between a set of technologies and the description of an environment. This greatly simplifies the specification process.

Unfortunately, there was not enough time in the project to both capture this detailed analysis and devise an automated optimization tool to distill its results that could be verified to be more accurate than expert opinion. Therefore, while we made the analysis as objective and specific as possible, no such analysis can be performed without the need for educated judgment and this was applied.

Aggregated Requirements Approach. In parallel, the 20 IntelliGrid Architecture Environments with their characterizing Aggregated Requirements were linked to the standard technologies, common services, and best practices, using expert opinion from IntelliGrid Architecture team’s combined deep and broad experience in the utility and communications industries. Although this approach might have permitted some bias, it was believed that the checks and balances of the different experiences of the team members, combined with long, in depth discussions of the different technologies, have prevented any substantive bias.

This spreadsheet was then used to create documents for each Environment, listing the categorizing Aggregated Requirements and the associated links. These Environments can be found in Volume IV Appendix E and on IntelliGrid Architecture website.

IntelliGrid Architecture Web Pages/Website

The IntelliGrid Architecture, the results of these analyses and linkages, along with the key discussions on communication architectural issues were designed to be directly migrated onto IntelliGrid Architecture website. This website will permit users to have more direct access to IntelliGrid Architecture work through standard browsing techniques.

IntelliGrid Architecture is indeed a member of the digital society.

Areas Beyond the Scope of IntelliGrid Architecture

IntelliGrid Architecture makes no recommendations in the following areas because they are considered to be beyond the scope of this project.


Table 7: Areas beyond the scope of IntelliGrid Architecture.

Name

Description

Reasons for Exclusion

Exceptions

User Interface

All information exchanges that were identified as occurring between people and devices in the use cases.

Do not address communications between computer systems.

None.

Industry Organizational Changes

Changes to the overall business and regulatory structure of the industry.

Not technological issues.

Sometimes discussed with respect to a single organization, as needed to deploy particular strategies such as security.

Algorithms and Applications

Details of particular algorithms, such as load shedding, volt/VAR control, or auto-restoration.

Subject to rapid change and innovation, and therefore not a part of a long-term architectural specification.

Where the requirements of particular applications have a specific effect on the com­munications system, e.g. protection in general, but not specific protection schemes.

Electrical Power Trends

Emerging trends or ideas that have solely to do with the power system, e.g. the use of more DC links

Not communications issues.

Where trends have an impact on the communications system, e.g. the trend to using more DC links does not affect communications, but the trend to more demand-side management does.

Electronic Media

Applications involving the transmission of audio or video within the power system communications network.

To limit the scope, since the logistics and bandwidth needed to implement such applications may outweigh their benefits.

None.

 

IntelliGrid Project cannot mandate – only recommend

Architecture documents formally developed by enterprises and government are typically characterized by calling out the use of ‘mandated’ standards (and associated technologies) as well as ‘candidate’ standards for use in developing information systems.  Mandated standards are those that must be adhered to while candidate standards are those that are maturing and may be mandated at a later date.  The IntelliGrid Architecture project does not have a charter to mandate use, and therefore may only recommend use and back these recommendations with analysis.  Users may review both the recommendations as well as the supporting analysis to determine the strength of the recommendation.

Not the Final Word

The work of IntelliGrid Architecture is not done.  In fact, it has only just started. As noted in the Project Summary, three key steps of system architecture design remain to be executed:

§       Testing the principles of the architecture in prototypes and pilot projects.

§       Implementation and validation of the design in real-world, large-scale systems.

§       Integration of the lessons learned into further iterations of the process.

In addition, for the vision of a safe, self-healing, reliable, optimized, and customer-integrated power network to be realized, the industry must make a cultural and organizational commitment to the concept of a common architecture. 

For we must admit to ourselves that the digital society has arrived, and we definitely must ensure our industry becomes part of it; but most importantly, we must realize that it is our responsibility to keep it running.



[2] Kurt Yeager, EPRI CEO in an August 25, 2003 interview on the Lehrer News Hour about the August 14, 2003 East Coast Blackout.

[3] IEEE STD 1471, 2001

[4] Hirst, Eric; “Transmission Planning for a New Era”; 1/2004; http://www.ehirst.com/PDF/TXPlanning102.PDF

[5] IEEE STD 1471, 2001

[6] Unified Modeling Language and UML are registered trademarks of the Object Management Group, Inc.

[7] IEEE 610.12

[8] NIST, “Automated Knowledge Discovery System (AKDS)”, ATP, 2002

[9] ISO/IEC 19793 Open Distributed Processing-Reference Model-Use of UML for ODP viewpoints specifications – Working Draft.

 